7245-7247 N IRVINE AVE 91605
Certificate Information: 7245-7247 N IRVINE AVE 91605
- Application / Permit
- 21016-20000-25979
- Plan Check / Job No.
- B21VN12284
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 19'-3" X 24'-0" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 10/20/2021
- Issuing Office
- Current Status
- CofO Issued on 9/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2021 | JENNIFER LEE |
| Corrections Issued | 9/15/2021 | JENNIFER LEE |
| Plan Check Approved | 10/18/2021 | JENNIFER LEE |
| Issued | 10/20/2021 | APPLICANT |
| Building Plans Picked Up | 8/24/2022 | APPLICANT |
| CofO in Progress | 9/6/2023 | DAVID MATSON |
| CofO Issued | 9/11/2023 | RUBEN SALAS |
| Permit Finaled | 9/11/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/22/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/9/2021 | No Access for Inspection | MATT KELLERMAN |
| BUILDING-Rough-Frame | 11/30/2021 | Partial Inspection | CALEB MEISTER |
| Green Building Rough | 11/30/2021 | Partial Inspection | CALEB MEISTER |
| PLUMBING-Rough | 11/30/2021 | Partial Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 12/7/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 12/7/2021 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 3/4/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 3/8/2022 | Corrections Issued | MATT KELLERMAN |
| PLUMBING-Rough | 3/8/2022 | Corrections Issued | MATT KELLERMAN |
| BUILDING-Rough-Frame | 3/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 3/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 4/4/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 4/4/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 4/4/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 5/12/2022 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 5/13/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/7/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 6/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/22/2022 | Corrections Issued | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 6/22/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 7/29/2022 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 9/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 9/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 9/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 9/22/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/22/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 12/27/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 12/27/2022 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 12/27/2022 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 12/27/2022 | Partial Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 1/9/2023 | Corrections Issued | JOHN HAYES |
| HVAC-Rough | 1/9/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 1/9/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Rough | 3/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 3/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 4/25/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 4/25/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 4/25/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 4/25/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 4/25/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/6/2023 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 6/6/2023 | Approved | JOHN HAYES |
| Green Building Rough | 6/6/2023 | Approved | JOHN HAYES |
| HVAC-Rough | 6/6/2023 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/14/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 6/14/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/29/2023 | Approved | JOHN HAYES |
| Insulation | 6/29/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 6/29/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 7/13/2023 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/2/2023 | Approved | JOHN HAYES |
| Final | 8/2/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 8/2/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/2/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 8/2/2023 | Approved | JOHN HAYES |
| Final | 8/11/2023 | OK to Issue CofO | DAVID MATSON |