5923 1/2 S HAAS AVE 90047

Certificate Information: 5923 1/2 S HAAS AVE 90047

Application / Permit
21016-20000-25394
Plan Check / Job No.
B21VN12152
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). Comply with Department Order effective date 03/14/2020
Permit Issued
Issued on 1/17/2022
Issuing Office
Current Status
CofO Issued on 4/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2021 APPLICANT
Assigned to Plan Check Engineer 9/10/2021 JEROME MAGAT PALMA
Corrections Issued 9/12/2021 JEROME MAGAT PALMA
Issued 1/17/2022 APPLICANT
Building Plans Picked Up 1/18/2022 APPLICANT
CofO in Progress 4/4/2025 GABRIEL HERRERA
CofO in Progress 4/4/2025 HAGOP BADOSSIAN
Permit Finaled 4/8/2025 DANIEL SANCHEZ
CofO Issued 4/8/2025 DANIEL SANCHEZ
Permit Finaled 4/8/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 9/22/2021 CELINA MORENO
Sewer availability Cleared 9/22/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/28/2021 CELINA MORENO
CPC Cleared 11/1/2021 PABLO ESTRADA
Construction near power lines Cleared 12/27/2021 WALTER RAMIREZ

Contact Information

No Data Available.

Inspector Information

EDMUND LUM, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
LUCIANO GAUNA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
JAIME RIOS, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
ANDEY CHAPARRO, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
RYAN BARNES, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
PATRICK LIEBREGT, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GLEN RAND, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
SHAWN ESHBACH, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GABRIEL HERRERA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/24/2023 Approved NEVILLE REID
BUILDING-Rough-Frame 4/4/2025 Approved GABRIEL HERRERA
Final 4/4/2025 Conditional Approval GABRIEL HERRERA
Green Building Final 4/4/2025 Approved GABRIEL HERRERA
Green Building Rough 4/4/2025 Approved GABRIEL HERRERA
METHANE-Final 4/4/2025 Approved GABRIEL HERRERA
METHANE-Rough 4/4/2025 Approved GABRIEL HERRERA
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Approved GABRIEL HERRERA
Smoke Detectors 4/4/2025 Approved GABRIEL HERRERA