14915 W SYLVAN ST 91411

Certificate Information: 14915 W SYLVAN ST 91411

Application / Permit
21016-20000-24073
Plan Check / Job No.
B21VN12046
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/9/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2021 APPLICANT
Assigned to Plan Check Engineer 9/8/2021 GURUNATH NESARAJAH
Corrections Issued 9/13/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 12/1/2021 GURUNATH NESARAJAH
Plan Check Approved 12/18/2021 GURUNATH NESARAJAH
Building Plans Picked Up 12/22/2021 APPLICANT
Issued 2/9/2022 APPLICANT
CofO in Progress 8/15/2022 RICHARD DOCKUS
Permit Finaled 8/17/2022 RONALD MYRICK
CofO Issued 8/17/2022 RONALD MYRICK
Permit Finaled 8/17/2022 RONALD MYRICK

Permit Application Clearance Information

Construction near power lines Cleared 11/21/2021 RIDWAN HARDY
Address approval Cleared 11/22/2021 CARLOS AGUILERA
Sewer availability Cleared 11/22/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/23/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/15/2022 Approved RICHARD DOCKUS
Sewer 4/15/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 4/20/2022 Partial Approval RICHARD DOCKUS
Gas Test 4/26/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 5/12/2022 Not Ready for Inspection RAUL OLAGI
Green Building Rough 5/12/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 5/24/2022 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 5/24/2022 Approved RICHARD DOCKUS
Green Building Rough 5/24/2022 Approved RICHARD DOCKUS
HVAC-Rough 5/24/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 5/24/2022 Approved RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 5/24/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/2/2022 Approved RICHARD DOCKUS
Insulation 6/2/2022 Approved RICHARD DOCKUS
Drywall Nailing 6/13/2022 Approved DAVID MATSON
Interior/Exterior Lathing 6/13/2022 Partial Approval DAVID MATSON
Final 8/1/2022 Corrections Issued RICHARD DOCKUS
Green Building Final 8/1/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 8/1/2022 Approved RICHARD DOCKUS
Final 8/5/2022 No Access for Inspection RICHARD DOCKUS
Final 8/12/2022 OK to Issue CofO RICHARD DOCKUS