18651 W BRYMER ST 91326

Certificate Information: 18651 W BRYMER ST 91326

Application / Permit
21016-20000-24042
Plan Check / Job No.
B21VN12033
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED IRR. SHAPE 58'5" X 23'6" ADDITION TO REAR OF (E) SFD. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 1/23/2022
Issuing Office
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 GURUNATH NESARAJAH
Corrections Issued 9/11/2021 GURUNATH NESARAJAH
Plan Check Approved 1/14/2022 SAMUEL GONZALEZ
Issued 1/23/2022 APPLICANT
Building Plans Picked Up 1/27/2022 APPLICANT
CofO in Progress 12/12/2022 DAVID SCANTLIN
Permit Finaled 2/15/2023 DANIEL ORRANTE
CofO Issued 2/15/2023 DANIEL ORRANTE
Permit Finaled 2/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/19/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 10/19/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 10/19/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 10/19/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 10/19/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 10/20/2021 DAGOVERTO GUERRERO
ZA Case Cleared 10/20/2021 DANG NGUYEN
Low Impact Development Cleared 12/21/2021 TA ANH
Roof/Waste drainage to street Cleared 1/5/2022 DAGOVERTO GUERRERO
GPI Written Notices Cleared 1/14/2022 GURUNATH NESARAJAH
Grading Pre-Inspection Cleared 1/14/2022 GURUNATH NESARAJAH

Contact Information

Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 21520 BURBANK BLVD APT 219      WOODLAND HILLS, CA 91367

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/8/2022 Approved DAVID SCANTLIN
Footing/Foundation/Slab 2/8/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 2/8/2022 Partial Approval DAVID SCANTLIN
Reinforced Concrete Frame 2/8/2022 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 3/16/2022 Not Ready for Inspection DAVID SCANTLIN
Sewer 3/16/2022 Approved DAVID SCANTLIN
ELECTRICAL-Rough 4/5/2022 Approved DAVID SCANTLIN
HVAC-Rough 4/5/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 4/5/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 4/7/2022 Approved DAVID SCANTLIN
Green Building Rough 4/7/2022 Approved DAVID SCANTLIN
Interior/Exterior Lathing 4/7/2022 Partial Approval DAVID SCANTLIN
Insulation 4/13/2022 Approved JUSTIN HAWLEY
Drywall Nailing 4/20/2022 Approved JUSTIN HAWLEY
Drywall Nailing 4/21/2022 Approved JUSTIN HAWLEY
Service/Power Release 6/23/2022 Not Ready for Inspection DAVID SCANTLIN
Final 10/5/2022 Corrections Issued DAVID SCANTLIN
Green Building Final 10/5/2022 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved DAVID SCANTLIN
Service/Power Release 10/5/2022 Not Required DAVID SCANTLIN
Smoke Detectors 10/5/2022 Approved DAVID SCANTLIN
Final 12/8/2022 OK to Issue CofO DAVID SCANTLIN
Green Building Final 12/8/2022 Approved DAVID SCANTLIN