11154 N LOUISE AVE 91344

Certificate Information: 11154 N LOUISE AVE 91344

Application / Permit
21016-20000-23805
Plan Check / Job No.
B20VN00804
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 12'-6" x 20'-3" PATIO COVER AND CONVERT 18'-2" x 20'-3" (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). SEE COMMENTS
Permit Issued
Issued on 5/17/2023
Issuing Office
Valley
Current Status
Issued on 5/17/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/17/2020 APPLICANT
Green Plans Picked Up 2/21/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 SARKIS HARABEDIAN
Corrections Issued 3/9/2020 SARKIS HARABEDIAN
Quality Review Completed 3/12/2020 GUANG MIN TUNG
Applicant returned to address corrections 8/28/2020 SARKIS HARABEDIAN
Applicant returned to address corrections 9/2/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 10/18/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 2/3/2022 SARKIS HARABEDIAN
Plan Check Approved 4/1/2022 SARKIS HARABEDIAN
Building Plans Picked Up 4/25/2022 APPLICANT
Issued 5/17/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/13/2021 CARLOS AGUILERA
Sewer availability Cleared 11/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/15/2021 CARLOS AGUILERA
Address approval Cleared 11/24/2021 CARLOS AGUILERA
Construction near power lines Cleared 3/12/2022 RIDWAN HARDY

Contact Information

Architect Friedman,, John Benjamin; Lic. No.: C9167 23427 BLYTHE STREET      WEST HILLS, CA 91304
Contractor Owner-Builder       ,
Engineer Avila,, Albert Guerrero; Lic. No.: C41726 10034 GLADE AVNENUE      CHATSWORTH, CA 91311

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/24/2023 Corrections Issued STEVEN BACK
PLUMBING-Rough 5/24/2023 Partial Approval STEVEN BACK
Special/Order Compliance 5/24/2023 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 6/7/2023 Partial Approval STEVEN BACK
PLUMBING-Rough 6/7/2023 Partial Approval STEVEN BACK
Deputy Drilled-In Anchors 6/12/2023 Conditional Approval STEVEN BACK
Deputy Wood Construction 6/12/2023 Conditional Approval STEVEN BACK
ELECTRICAL-Rough 6/28/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Approved STEVEN BACK
HVAC-Rough 6/28/2023 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 6/28/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 7/3/2023 Partial Approval STEVEN BACK
Green Building Rough 7/3/2023 Approved STEVEN BACK
Insulation 7/3/2023 Approved STEVEN BACK
Special/Order Compliance 7/3/2023 Corrections Issued STEVEN BACK
Drywall Nailing 7/12/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 1/10/2025 Corrections Issued STEVEN BACK
Final 1/10/2025 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 1/10/2025 SGSOV Not Ready STEVEN BACK
Smoke Detectors 1/10/2025 Approved STEVEN BACK