433-433 1/2 E 29TH ST 90011

Certificate Information: 433-433 1/2 E 29TH ST 90011

Application / Permit
21016-20000-23369
Plan Check / Job No.
B21VN11868
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT EX DETACHED 50'3"X30'2" 1ST FLR GARAGE OF EX 2-STORY DUPLEX W/ GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). SEE COMMENTS.
Permit Issued
Issued on 6/15/2023
Issuing Office
Metro
Current Status
Issued on 6/15/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/1/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 HAYATO TSUCHIYA
Corrections Issued 10/5/2021 HAYATO TSUCHIYA
Quality Review Completed 10/8/2021 STEVEN KIM
Applicant returned to address corrections 3/8/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 4/15/2022 HAYATO TSUCHIYA
Plan Check Approved 7/25/2022 HAYATO TSUCHIYA
Building Plans Picked Up 7/27/2022 APPLICANT
Issued 6/15/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/23/2021 CHRISTOPHER ROCHA
Tenant Habitability Plan Cleared 12/13/2021 RICHARD BRINSON
Address approval Cleared 12/16/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 12/16/2021 CHRISTOPHER ROCHA

Contact Information

Contractor Caribe Construction Inc; Lic. No.: 878090-B 521 S PARISH PLACE      BURBANK, CA 91506
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 7/21/2023 No Access for Inspection BRENDAN MORELLI
METHANE-Rough 7/21/2023 No Access for Inspection BRENDAN MORELLI
Wood Frame 7/21/2023 No Access for Inspection BRENDAN MORELLI
Pre-Inspection 7/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 7/27/2023 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/15/2023 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 12/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Rough 12/20/2023 Not Ready for Inspection ALEJANDRO DE ARTOLA
Wood Frame 12/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 2/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 3/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/22/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 4/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 4/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval ALEJANDRO DE ARTOLA
Insulation 5/23/2024 Partial Approval ALEJANDRO DE ARTOLA
Wood Frame 5/23/2024 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/28/2024 Partial Approval ALEJANDRO DE ARTOLA
Pre-Inspection 2/26/2025 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 2/26/2025 Partial Inspection MICHAEL LEWIS
Pre-Inspection 3/11/2025 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/4/2026 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/27/2026 Partial Approval LUIS CASTRO
Green Building Rough 4/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 4/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/6/2026 Partial Approval ALEX COLIN
Green Building Rough 4/8/2026 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 4/8/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 4/16/2026 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 4/16/2026 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 4/16/2026 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 4/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 4/23/2026 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 4/23/2026 Conditional Approval ALEJANDRO DE ARTOLA
Drywall Nailing 4/28/2026 Approved ALEX COLIN