2715 S ANCHOR AVE 90064
Certificate Information: 2715 S ANCHOR AVE 90064
- Application / Permit
- 21016-20000-23332
- Plan Check / Job No.
- B21VN11852
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) SFD FOR (N) KITCHEN, DINING ROOM, BATHROOMS, CLOSETS, BEDROOM AND STUDY ROOM.
- Permit Issued
- Issued on 11/18/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/5/2022
Permit Application Status History
| Submitted | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/2/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/12/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 10/27/2021 | RAPHAEL ROSAS |
| Issued | 11/18/2021 | APPLICANT |
| Building Plans Picked Up | 11/22/2021 | APPLICANT |
| Permit Finaled | 8/4/2022 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 9/28/2021 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 10/5/2021 | SAUL GARCIA |
Contact Information
| Contractor | Dh Remodel Services; Lic. No.: 1030925-B | 5850 W 3RD STREET #160 LOS ANGELES, CA 90036 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/15/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 2/15/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 2/18/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/18/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/4/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/8/2022 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/8/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/8/2022 | Corrections Issued | KEVIN SARGSYAN |
| Rough-Elec/Plmb/HVAC | 3/8/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 3/11/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/11/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/16/2022 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 3/24/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/30/2022 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 3/30/2022 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 4/1/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Wood Frame | 4/1/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 4/6/2022 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 4/6/2022 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 4/7/2022 | Approved | KEVIN SARGSYAN |
| Shower Pan | 4/8/2022 | No Access for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/26/2022 | Approved | KEVIN SARGSYAN |
| Insulation | 5/26/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/26/2022 | Approved | KEVIN SARGSYAN |
| Wood Frame | 5/26/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/28/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 7/28/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 7/28/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 7/28/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/28/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/2/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 8/2/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 8/2/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/2/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/2/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/4/2022 | Approved | JOHNNY MIRANDA |
| Final | 8/4/2022 | Permit Finaled | JOHNNY MIRANDA |
| HVAC-Final | 8/4/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 8/4/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 8/4/2022 | Not Ready for Inspection | JOHNNY MIRANDA |