6631-6633 N BELMAR AVE 91335

Certificate Information: 6631-6633 N BELMAR AVE 91335

Application / Permit
21016-20000-23049
Plan Check / Job No.
B21VN11747
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert (E) Attached Garage (360 SF) and portion of (E) Single Family Dwelling (180 SF) to Accessory Dwelling Unit (ADU) per Oridnance (540 SF)
Permit Issued
Issued on 2/1/2022
Issuing Office
Current Status
CofO Corrected on 9/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2021 APPLICANT
Assigned to Plan Check Engineer 8/31/2021 HERNAN ARREOLA
Corrections Issued 9/16/2021 HERNAN ARREOLA
Applicant returned to address corrections 11/23/2021 HERNAN ARREOLA
Plan Check Approved 1/3/2022 HERNAN ARREOLA
Issued 2/1/2022 APPLICANT
CofO in Progress 8/27/2022 VINCENT HANLEY
Re-Activate Permit 9/30/2022 JOHN JANSON
CofO Issued-Status Void 9/30/2022 JOHN JANSON
Permit Finaled-Status Void 9/30/2022 JOHN JANSON
Permit Finaled 9/30/2022 JOHN JANSON
CofO Corrected 9/30/2022 JOHN JANSON
Permit Finaled 9/30/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/28/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/28/2021 CARLOS AGUILERA
Sewer availability Cleared 12/28/2021 CARLOS AGUILERA

Contact Information

Contractor O C Builders Group Inc; Lic. No.: 1052090-B 600 W SANTA ANA BLVD   SUITE 114A-499    SANTA ANA, CA 92701

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/10/2022 Approved VINCENT HANLEY
PLUMBING-Rough 2/10/2022 Approved VINCENT HANLEY
Sewer 2/10/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 2/23/2022 Approved VINCENT HANLEY
Insulation 2/23/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/9/2022 Approved VINCENT HANLEY
Green Building Rough 3/9/2022 Approved VINCENT HANLEY
HVAC-Rough 3/9/2022 Approved VINCENT HANLEY
Insulation 3/9/2022 Approved VINCENT HANLEY
Drywall Nailing 3/15/2022 Approved MORRIS JACKSON
Gas Test 3/15/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/15/2022 Approved MORRIS JACKSON
ELECTRICAL-Final 7/25/2022 Approved JEFFREY BULL
Final 7/25/2022 Not Ready for Inspection JEFFREY BULL
Green Building Final 7/25/2022 Not Ready for Inspection JEFFREY BULL
HVAC-Final 7/25/2022 Not Ready for Inspection JEFFREY BULL
PLUMBING-Final 7/25/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Approved JEFFREY BULL
Smoke Detectors 7/25/2022 Approved JEFFREY BULL
Final 8/9/2022 Not Ready for Inspection JEFFREY BULL
Green Building Final 8/9/2022 Approved JEFFREY BULL
Enclosure/Fence 8/10/2022 Corrections Issued JEFFREY BULL
Final 8/26/2022 OK to Issue CofO VINCENT HANLEY
HVAC-Final 8/26/2022 Approved VINCENT HANLEY