6631-6633 N BELMAR AVE 91335
Certificate Information: 6631-6633 N BELMAR AVE 91335
- Application / Permit
- 21016-20000-23049
- Plan Check / Job No.
- B21VN11747
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert (E) Attached Garage (360 SF) and portion of (E) Single Family Dwelling (180 SF) to Accessory Dwelling Unit (ADU) per Oridnance (540 SF)
- Permit Issued
- Issued on 2/1/2022
- Issuing Office
- Current Status
- CofO Corrected on 9/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2021 | HERNAN ARREOLA |
| Corrections Issued | 9/16/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/23/2021 | HERNAN ARREOLA |
| Plan Check Approved | 1/3/2022 | HERNAN ARREOLA |
| Issued | 2/1/2022 | APPLICANT |
| CofO in Progress | 8/27/2022 | VINCENT HANLEY |
| Re-Activate Permit | 9/30/2022 | JOHN JANSON |
| CofO Issued-Status Void | 9/30/2022 | JOHN JANSON |
| Permit Finaled-Status Void | 9/30/2022 | JOHN JANSON |
| Permit Finaled | 9/30/2022 | JOHN JANSON |
| CofO Corrected | 9/30/2022 | JOHN JANSON |
| Permit Finaled | 9/30/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/28/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/28/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | O C Builders Group Inc; Lic. No.: 1052090-B | 600 W SANTA ANA BLVD SUITE 114A-499 SANTA ANA, CA 92701 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/10/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/10/2022 | Approved | VINCENT HANLEY |
| Sewer | 2/10/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/23/2022 | Approved | VINCENT HANLEY |
| Insulation | 2/23/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/9/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 3/9/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/9/2022 | Approved | VINCENT HANLEY |
| Insulation | 3/9/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 3/15/2022 | Approved | MORRIS JACKSON |
| Gas Test | 3/15/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/15/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 7/25/2022 | Approved | JEFFREY BULL |
| Final | 7/25/2022 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Final | 7/25/2022 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Final | 7/25/2022 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 7/25/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 7/25/2022 | Approved | JEFFREY BULL |
| Final | 8/9/2022 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Final | 8/9/2022 | Approved | JEFFREY BULL |
| Enclosure/Fence | 8/10/2022 | Corrections Issued | JEFFREY BULL |
| Final | 8/26/2022 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 8/26/2022 | Approved | VINCENT HANLEY |