4834 S WILTON PL 90062
Certificate Information: 4834 S WILTON PL 90062
- Application / Permit
- 21016-20000-22984
- Plan Check / Job No.
- B21VN11700
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 2/11/2022
- Issuing Office
- Current Status
- CofO Issued on 7/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2021 | SERGIO MUNIZ |
| Corrections Issued | 9/5/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/5/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/19/2021 | SERGIO MUNIZ |
| Plan Check Approved | 10/27/2021 | SERGIO MUNIZ |
| Issued | 2/11/2022 | APPLICANT |
| Building Plans Picked Up | 2/16/2022 | APPLICANT |
| CofO in Progress | 7/3/2023 | SABAS ALONSO |
| Permit Finaled | 7/18/2023 | DEROLD HAUFF |
| CofO Issued | 7/18/2023 | DEROLD HAUFF |
| Permit Finaled | 7/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/4/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James W; Lic. No.: C43590 | 15315 BLEDSOE ST SYLMAR, CA 91342 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/22/2022 | Corrections Issued | ANTHONY EGSON |
| Pre-Inspection | 2/22/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/1/2022 | Corrections Issued | SABAS ALONSO |
| Pre-Inspection | 3/1/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 3/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 3/17/2022 | Partial Approval | SABAS ALONSO |
| Deputy Drilled-In Anchors | 3/21/2022 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/13/2022 | No Access for Inspection | SABAS ALONSO |
| Green Building Rough | 4/13/2022 | No Access for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 4/13/2022 | No Access for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 4/29/2022 | Approved | SABAS ALONSO |
| Pre-Inspection | 4/29/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 8/3/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/3/2022 | Not Ready for Inspection | SABAS ALONSO |
| Wood Frame | 8/3/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 8/19/2022 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 8/22/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/2/2022 | Approved | ANDREW BEELI |
| HVAC-Rough | 9/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| BUILDING-Rough-Frame | 9/14/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 9/14/2022 | Approved | SABAS ALONSO |
| Insulation | 9/14/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 9/22/2022 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 9/22/2022 | Approved | SABAS ALONSO |
| Shower Pan | 9/22/2022 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 10/3/2022 | Not Ready for Inspection | HORACE FULTZ |
| Shower Pan | 10/3/2022 | Corrections Issued | HORACE FULTZ |
| Drywall Nailing | 10/6/2022 | Approved | RYAN SALAZAR |
| Shower Pan | 10/6/2022 | Approved | RYAN SALAZAR |
| Final | 12/19/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/19/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 12/19/2022 | Approved | SABAS ALONSO |
| Final | 1/17/2023 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 1/17/2023 | Approved | SABAS ALONSO |
| Final | 5/19/2023 | Corrections Issued | SABAS ALONSO |
| Final | 6/26/2023 | Corrections Issued | SABAS ALONSO |
| Final | 6/30/2023 | OK to Issue CofO | SABAS ALONSO |