22333 W SHERMAN WAY 91303

Certificate Information: 22333 W SHERMAN WAY 91303

Application / Permit
21016-20000-22794
Plan Check / Job No.
B21VN11671
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Grocery Store
Work Description
*ePlan Check* TENANT IMPROVEMENT TO (E) GROCERY STORE. REPLACING REFRIGERATED CASES IN DELI & BAKERY DEPARTMENTS; ADDING NEW SINK IN PRODUCE PREP; REPLACING OLD TABLES AND CASES IN PRODUCE SALES; REPLACING OLD CASES IN DELI/BAKERY DEPARTMENT; REPLACING OLD GONDOLAS ON SALES FLOOR; ADDING NEW DECOR ON SALES FLOOR.
Permit Issued
Issued on 8/23/2022
Issuing Office
Current Status
Permit Finaled on 2/23/2024

Permit Application Status History

Submitted 8/30/2021 APPLICANT
Assigned to Plan Check Engineer 9/1/2021 HERNAN ARREOLA
Corrections Issued 9/1/2021 HERNAN ARREOLA
Plan Check Approved 10/7/2021 HERNAN ARREOLA
Issued 8/23/2022 APPLICANT
Permit Finaled 2/22/2024 BRIAN KELLY

Permit Application Clearance Information

Food establishment approval Cleared 10/7/2021 LACDHS APPROVED

Contact Information

Architect , ; Lic. No.: NA30604       ,
Contractor B S M Construction Inc; Lic. No.: 828014-B 2575 STANWELL DRIVE 2ND FLOOR      CONCORD, CA 94520

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/30/2022 Conditional Approval DANIEL VARNUM
Grading Pre-Inspection 10/27/2022 Corrections Issued DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 12/14/2022 Partial Approval DANIEL VARNUM
Grading Pre-Inspection 12/29/2022 Not Ready for Inspection BRIAN KELLY
Excavation/Setback/Form/Re-Bar 12/30/2022 Corrections Issued DANIEL VARNUM
Deputy Reinf. Concrete 11/2/2023 Conditional Approval BRIAN KELLY
Final 11/7/2023 Not Ready for Inspection DANIEL VARNUM
Green Building Final 11/7/2023 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 11/7/2023 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 11/7/2023 Not Ready for Inspection DANIEL VARNUM
Final 11/28/2023 Not Ready for Inspection BRIAN KELLY
Green Building Final 11/28/2023 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 11/28/2023 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 11/28/2023 Not Ready for Inspection BRIAN KELLY
Final 2/22/2024 Permit Finaled BRIAN KELLY
Green Building Final 2/22/2024 Approved BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 2/22/2024 SGSOV Approved BRIAN KELLY
Smoke Detectors 2/22/2024 Approved BRIAN KELLY