4854 W PICO BLVD 90019

Certificate Information: 4854 W PICO BLVD 90019

Application / Permit
21016-20000-22737
Plan Check / Job No.
B21VN11628
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
T.I. AND CHG OF USE FROM BEAUTY SALON TO RETAIL/OFFICE & STOREFRONT REMODEL (63'-8" x 33')
Permit Issued
Issued on 12/10/2021
Issuing Office
Current Status
CofO Issued on 3/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2021 APPLICANT
Disabled Access Plans Picked Up 9/21/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 SEAN SHAHMIRI
Corrections Issued 10/5/2021 SEAN SHAHMIRI
Quality Review Completed 10/5/2021 OMID HEDAYAT
Building Plans Picked Up 10/6/2021 APPLICANT
Plan Check Approved 12/6/2021 SEAN SHAHMIRI
Issued 12/10/2021 APPLICANT
CofO in Progress 3/30/2022 DARRYL ARNOLD
Permit Finaled 3/30/2022 WINSTON DUNNING
CofO Issued 3/30/2022 WINSTON DUNNING
Permit Finaled 3/30/2022 WINSTON DUNNING

Permit Application Clearance Information

Miscellaneous Cleared 10/19/2021 STEVEN WECHSLER
Miscellaneous Cleared 10/19/2021 STEVEN WECHSLER
Miscellaneous Cleared 10/19/2021 STEVEN WECHSLER
Miscellaneous Cleared 10/19/2021 STEVEN WECHSLER
Miscellaneous Cleared 10/19/2021 STEVEN WECHSLER
Miscellaneous Cleared 10/19/2021 STEVEN WECHSLER
ZA Case Cleared 10/19/2021 STEVEN WECHSLER
Redevelopment Project Area Cleared 10/27/2021 GRACIELA ACOSTA
Eng Process Fee Ord 176,300 Cleared 11/4/2021 JEANIE LAM
DAS Clearance Cleared 11/16/2021 OLLIE CARTER
Sewer availability Cleared 11/18/2021 JEANIE LAM

Contact Information

Architect Nouizi,, Ilyes M; Lic. No.: C32135 14252 CULVER DRIVE SUITE A-605      IRVINE, CA 92604
Contractor Market Contractors Ltd; Lic. No.: 545305-B 10250 NE MARX ST      PORTLAND, OR 97220

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/27/2022 Approved KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 1/27/2022 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/8/2022 Approved KATY RAMIREZ
Special/Order Compliance 2/11/2022 Corrections Issued KATY RAMIREZ
T-Bar Ceiling 3/3/2022 Partial Inspection KATY RAMIREZ
METHANE-Final 3/16/2022 Not Ready for Inspection KATY RAMIREZ
METHANE-Rough 3/16/2022 Not Ready for Inspection KATY RAMIREZ
Reinforced Masonry Frame 3/16/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 3/16/2022 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 3/16/2022 Not Ready for Inspection KATY RAMIREZ
Final 3/21/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 3/21/2022 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 3/21/2022 Approved KATY RAMIREZ
Final 3/23/2022 Not Ready for Inspection DARRYL ARNOLD
Special/Order Compliance 3/24/2022 Conditional Approval DARRYL ARNOLD
Special/Order Compliance 3/25/2022 Conditional Approval DARRYL ARNOLD
Final 3/30/2022 Conditional Approval DARRYL ARNOLD