5538-5540 N DENNY AVE 91601

Certificate Information: 5538-5540 N DENNY AVE 91601

Application / Permit
21016-20000-22683
Plan Check / Job No.
B21VN11599
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert portion (467sf) of the (e) SFD to a new Accessory Dwelling Unit Remodel (e) kitchen and add powder room. 2ND FLOOR REMODEL TO BEDROOM. ADD CLOSET.
Permit Issued
Issued on 9/7/2021
Issuing Office
Current Status
CofO Issued on 2/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2021 APPLICANT
Assigned to Plan Check Engineer 8/30/2021 JOE VO
Corrections Issued 8/30/2021 JOE VO
Plan Check Approved 9/1/2021 JOE VO
Issued 9/7/2021 APPLICANT
CofO in Progress 1/25/2022 MICHAEL TEMPLE
Permit Finaled 2/22/2022 MICHAEL SMITH
CofO Issued 2/22/2022 MICHAEL SMITH
Permit Finaled 2/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/31/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/31/2021 CARLOS AGUILERA
Sewer availability Cleared 8/31/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/13/2021 Approved ARAM AVEDISIAN
HVAC-Rough 10/13/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 10/13/2021 Approved ARAM AVEDISIAN
Wood Frame 10/13/2021 Partial Approval ARAM AVEDISIAN
Insulation 10/18/2021 Approved DANIEL DREW
Shower Pan 10/21/2021 Approved DANIEL DREW
Drywall Nailing 10/27/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/27/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/14/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Final 12/14/2021 Approved ARAM AVEDISIAN
Final 12/14/2021 Corrections Issued ARAM AVEDISIAN
HVAC-Final 12/14/2021 Approved ARAM AVEDISIAN
METHANE-Final 12/14/2021 Approved ARAM AVEDISIAN
METHANE-Rough 12/14/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 12/14/2021 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 12/14/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Final 12/16/2021 Not Ready for Inspection JOHN HAYES
Final 12/16/2021 Corrections Issued JOHN HAYES
HVAC-Final 12/16/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 12/16/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 1/10/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 1/10/2022 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Final 1/10/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 1/10/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Service/Power Release 1/10/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 1/20/2022 Approved JENNIFER RABUCHIN
Final 1/20/2022 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 1/20/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/20/2022 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 1/24/2022 Approved MICHAEL TEMPLE
Final 1/24/2022 OK to Issue CofO MICHAEL TEMPLE