17743 W VANOWEN ST 91335

Certificate Information: 17743 W VANOWEN ST 91335

Application / Permit
21016-20000-22592
Plan Check / Job No.
B21VN11572
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 11/19/2021
Issuing Office
Current Status
Issued on 11/19/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/25/2021 APPLICANT
Assigned to Plan Check Engineer 9/3/2021 ROSENDO MEDINA
Corrections Issued 9/4/2021 ROSENDO MEDINA
Applicant returned to address corrections 11/4/2021 ROSENDO MEDINA
Plan Check Approved 11/19/2021 ROSENDO MEDINA
Issued 11/19/2021 APPLICANT
Building Plans Picked Up 11/24/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/27/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 10/27/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 10/28/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/10/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/20/2021 Corrections Issued PETER FOLLING
PLUMBING-Rough 12/20/2021 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 1/13/2022 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 1/13/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 1/13/2022 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 1/21/2022 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 1/21/2022 Not Ready for Inspection VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 1/21/2022 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 1/21/2022 Corrections Issued VINCENT HANLEY
Green Building Rough 1/21/2022 Not Ready for Inspection VINCENT HANLEY
Deputy Drilled-In Anchors 1/31/2022 Conditional Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 2/2/2022 Not Ready for Inspection VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 2/2/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 2/2/2022 Approved VINCENT HANLEY
PLUMBING-Rough 2/28/2022 Partial Approval VINCENT HANLEY
Sewer 2/28/2022 Approved VINCENT HANLEY
PLUMBING-Rough 3/9/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 4/25/2022 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 4/28/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 4/28/2022 Approved VINCENT HANLEY
PLUMBING-Rough 4/28/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/6/2022 Approved VINCENT HANLEY
Green Building Rough 5/6/2022 Approved VINCENT HANLEY
HVAC-Rough 5/6/2022 Approved VINCENT HANLEY
Insulation 5/6/2022 Partial Approval VINCENT HANLEY
Drywall Nailing 5/12/2022 Approved MORRIS JACKSON
Final 6/1/2022 Corrections Issued VINCENT HANLEY
Green Building Final 6/1/2022 Approved VINCENT HANLEY
PLUMBING-Final 6/1/2022 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/1/2022 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 6/1/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 6/7/2022 Approved VINCENT HANLEY
Final 6/7/2022 Corrections Issued VINCENT HANLEY
HVAC-Final 6/7/2022 Approved VINCENT HANLEY
PLUMBING-Final 6/7/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/7/2022 SGSOV Approved VINCENT HANLEY