20051 W VENTURA BLVD 91364
Certificate Information: 20051 W VENTURA BLVD 91364
- Application / Permit
- 21016-20000-22523
- Plan Check / Job No.
- B21VN11521
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (10) Veterinary Hospital
- Work Description
- ePLAN. CHANGE OF USE FROM RETAIL TO VETERINARY CLINIC. INTERIOR TENANT IMPROVEMENT TO (E) VETERINARY CLINIC. NEW ROOFTOP EQUIPMENT.
- Permit Issued
- Issued on 2/14/2022
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2021 | KEVIN MORALES |
| Corrections Issued | 8/31/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 10/11/2021 | KEVIN MORALES |
| Plan Check Approved | 10/28/2021 | KEVIN MORALES |
| Issued | 2/14/2022 | APPLICANT |
| CofO in Progress | 12/30/2025 | BRIAN KELLY |
| Permit Finaled | 12/30/2025 | JEFFREY DURAN |
| CofO Issued | 12/30/2025 | JEFFREY DURAN |
| Permit Finaled | 12/30/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/15/2021 | CARLOS AGUILERA |
| Specific Plan | Cleared | 9/27/2021 | SHEILA AHORAIAN |
| "D" conditions | Cleared | 10/20/2021 | CORREY KITCHENS |
| Miscellaneous | Cleared | 10/20/2021 | CORREY KITCHENS |
| Miscellaneous | Cleared | 10/20/2021 | CORREY KITCHENS |
| Specific Plan | Cleared | 10/20/2021 | CORREY KITCHENS |
| ZA Case | Cleared | 10/20/2021 | CORREY KITCHENS |
| ZA Case | Cleared | 10/20/2021 | CORREY KITCHENS |
| ZA Case | Cleared | 10/20/2021 | CORREY KITCHENS |
Contact Information
| Contractor | Catamount Constructors Inc; Lic. No.: 760295-B | 1527 COLE BLVD STE 100 LAKEWOOD, CO 80401 |
| Engineer | Schell,, William Francis; Lic. No.: S4529 | 5550 BALTIMORE DRIVE STE 100 LA MESA, CA 91942 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/23/2022 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 2/23/2022 | Approved | DANIEL VARNUM |
| Drywall Nailing | 3/25/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 3/25/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 4/12/2022 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 5/3/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Footing/Foundation/Slab | 5/11/2022 | Conditional Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 5/25/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 5/31/2022 | Partial Approval | KENNETH ROBERTS |
| Light Gage Steel Frame | 6/2/2022 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 6/8/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 8/8/2022 | Partial Approval | DANIEL VARNUM |
| Final | 9/6/2022 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 9/6/2022 | Not Ready for Inspection | DANIEL VARNUM |
| T-Bar Ceiling | 9/6/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 9/6/2022 | Not Ready for Inspection | DANIEL VARNUM |
| T-Bar Ceiling | 9/15/2022 | Corrections Issued | ANDREW DORSO |
| T-Bar Ceiling | 9/19/2022 | Corrections Issued | DANIEL VARNUM |
| Final | 11/17/2022 | Corrections Issued | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Not Ready | ANDREW DORSO |
| Smoke Detectors | 11/17/2022 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 11/17/2022 | Not Ready for Inspection | ANDREW DORSO |
| T-Bar Ceiling | 6/22/2023 | Partial Approval | BRIAN KELLY |
| T-Bar Ceiling | 7/3/2023 | Partial Approval | BRIAN KELLY |
| Final | 8/3/2023 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 8/3/2023 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 8/3/2023 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 8/3/2023 | Approved | BRIAN KELLY |
| Final | 8/23/2023 | Not Ready for Inspection | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 8/23/2023 | SGSOV Not Ready | CAMERON CHABAN |
| Smoke Detectors | 8/23/2023 | Approved | CAMERON CHABAN |
| Final | 12/30/2025 | OK to Issue CofO | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Approved | BRIAN KELLY |