5629 N WILLIS AVE 91411
Certificate Information: 5629 N WILLIS AVE 91411
- Application / Permit
- 21016-20000-22102
- Plan Check / Job No.
- B21VN11411
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 10/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 9/10/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 1/22/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/19/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| Issued | 3/17/2022 | APPLICANT |
| CofO in Progress | 9/16/2022 | ALAN MORELOS |
| Permit Finaled | 10/11/2022 | MICHAEL SMITH |
| CofO Issued | 10/11/2022 | MICHAEL SMITH |
| Permit Finaled | 10/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/14/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 1/3/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/22/2022 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 3/22/2022 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 3/22/2022 | Corrections Issued | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 3/29/2022 | Not Ready for Inspection | DAVID MATSON |
| Footing/Foundation/Slab | 3/29/2022 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 3/29/2022 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 4/7/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 4/7/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 4/7/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 4/7/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 4/7/2022 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/14/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 4/14/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 4/14/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 4/14/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 4/14/2022 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/26/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/26/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/26/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 5/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 5/6/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/6/2022 | Approved | RICHARD DOCKUS |
| Insulation | 5/10/2022 | Partial Approval | ALAN MORELOS |
| Interior/Exterior Lathing | 5/13/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Insulation | 5/17/2022 | Corrections Issued | RICHARD DOCKUS |
| Insulation | 5/23/2022 | Partial Approval | ALAN MORELOS |
| Interior/Exterior Lathing | 5/23/2022 | Partial Approval | ALAN MORELOS |
| Drywall Nailing | 5/31/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Pre-Inspection | 9/1/2022 | Corrections Issued | RICHARD DOCKUS |
| Drywall Nailing | 9/3/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 9/12/2022 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 9/12/2022 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 9/12/2022 | SGSOV Approved | ROBERT GOLD |
| Smoke Detectors | 9/12/2022 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 9/14/2022 | Approved | ALAN MORELOS |
| Final | 9/14/2022 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Final | 9/14/2022 | Approved | ALAN MORELOS |
| HVAC-Final | 9/14/2022 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Final | 9/14/2022 | Approved | ALAN MORELOS |
| Final | 9/16/2022 | OK to Issue CofO | ALAN MORELOS |
| HVAC-Final | 9/16/2022 | Approved | ALAN MORELOS |