5943 N TOBIAS AVE 91411
Certificate Information: 5943 N TOBIAS AVE 91411
- Application / Permit
- 21016-20000-22078
- Plan Check / Job No.
- B21VN11391
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND STORAGE ROOM TO ACCESSORY DWELLING UNIT (630 SQ FT) PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Current Status
- CofO Issued on 7/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 8/29/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/1/2021 | APPLICANT |
| Issued | 9/13/2021 | APPLICANT |
| CofO in Progress | 5/31/2022 | RICHARD DOCKUS |
| Permit Finaled | 7/20/2022 | MICHAEL SMITH |
| CofO Issued | 7/20/2022 | MICHAEL SMITH |
| Permit Finaled | 7/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2021 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 9/3/2021 | PABLO ESTRADA |
| Miscellaneous | Cleared | 9/3/2021 | PABLO ESTRADA |
| Miscellaneous | Cleared | 9/3/2021 | PABLO ESTRADA |
| Sewer availability | Cleared | 9/3/2021 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 9/3/2021 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/22/2021 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 12/20/2021 | Approved | DAVID MATSON |
| Underground Mechanical | 12/20/2021 | Partial Approval | DAVID MATSON |
| ELECTRICAL-Rough | 1/26/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 1/26/2022 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 1/26/2022 | Corrections Issued | RICHARD DOCKUS |
| Wood Frame | 1/26/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 2/1/2022 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 2/1/2022 | Approved | ALAN MORELOS |
| Insulation | 2/4/2022 | Corrections Issued | ALAN MORELOS |
| Insulation | 2/8/2022 | Approved | ALAN MORELOS |
| Shower Pan | 2/8/2022 | Approved | ALAN MORELOS |
| Green Building Rough | 2/11/2022 | Approved | RICHARD DOCKUS |
| Insulation | 2/11/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 2/11/2022 | Partial Approval | RICHARD DOCKUS |
| Drywall Nailing | 2/17/2022 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 2/23/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 3/9/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 3/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| Sewer | 3/30/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 3/30/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 5/6/2022 | Approved | RICHARD DOCKUS |
| Final | 5/6/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 5/6/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/6/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 5/6/2022 | Approved | RICHARD DOCKUS |
| Final | 5/20/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/20/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| ELECTRICAL-Final | 5/27/2022 | Approved | RICHARD DOCKUS |
| Final | 5/27/2022 | OK to Issue CofO | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV Approved | RICHARD DOCKUS |