7019 N POMELO DR 91307
Certificate Information: 7019 N POMELO DR 91307
- Application / Permit
- 21016-20000-22071
- Plan Check / Job No.
- B21VN11387
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NON-STRUCTURAL INTERIOR REMODEL FOR (E) 1-STORY SFD - CONVERT 12'-10" X 14'-8" PORTION OF (E) LIVING ROOM TO (N) BEDROOM, REMODEL EXISTING BATHROOMS/BEDROOMS, REMOVE AND REPLACE EXISTING EXTERIOR WINDOWS/DOORS. ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/16/2021
- Issuing Office
- Current Status
- Issued on 9/16/2021
Permit Application Status History
| Submitted | 8/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2021 | JENNIFER LEE |
| Corrections Issued | 8/24/2021 | JENNIFER LEE |
| Plan Check Approved | 9/16/2021 | JENNIFER LEE |
| Issued | 9/16/2021 | APPLICANT |
| Building Plans Picked Up | 9/21/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/8/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/28/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 10/28/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 11/2/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 11/2/2021 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 11/8/2021 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 11/8/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 11/18/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 11/18/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 11/23/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Insulation | 11/23/2021 | Partial Approval | DAVID STEPANYAN |
| Interior/Exterior Lathing | 11/23/2021 | Partial Approval | DAVID STEPANYAN |
| Shower Pan | 11/23/2021 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 12/2/2021 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/2/2021 | Approved | JAVIER RAMOS JR |
| Final | 1/11/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/11/2022 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 1/11/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 1/13/2022 | Corrections Issued | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/13/2022 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 1/13/2022 | Approved | JUSTIN HAWLEY |