6933-6935 N COZYCROFT AVE 91306

Certificate Information: 6933-6935 N COZYCROFT AVE 91306

Application / Permit
21016-20000-22002
Plan Check / Job No.
B21VN11347
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 18'-1" X 20'-2" ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER WFPP.
Permit Issued
Issued on 12/28/2021
Issuing Office
Current Status
CofO Issued on 5/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2021 APPLICANT
Assigned to Plan Check Engineer 8/31/2021 RAPHAEL ROSAS
Corrections Issued 8/31/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/6/2021 RAPHAEL ROSAS
Issued 12/28/2021 APPLICANT
Building Plans Picked Up 1/4/2022 APPLICANT
CofO in Progress 5/11/2022 STEVEN BACK
CofO Issued 5/12/2022 MICHAEL SMITH
Permit Finaled 5/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/22/2021 CARLOS AGUILERA
Sewer availability Cleared 11/22/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/29/2021 CARLOS AGUILERA
ZI Cleared 12/1/2021 DANIEL CORONADO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/27/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 1/27/2022 Partial Approval STEVEN BACK
Footing/Foundation/Slab 1/31/2022 Approved STEVEN BACK
Deputy Drilled-In Anchors 2/1/2022 Approved JESUS PINEDA
BUILDING-Rough-Frame 2/14/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 2/14/2022 Corrections Issued STEVEN BACK
Green Building Rough 2/14/2022 Not Ready for Inspection STEVEN BACK
HVAC-Rough 2/14/2022 Approved STEVEN BACK
PLUMBING-Rough 2/14/2022 Approved STEVEN BACK
Sewer 2/14/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 2/24/2022 Conditional Approval STEVEN BACK
ELECTRICAL-Rough 2/24/2022 Approved STEVEN BACK
Green Building Rough 2/24/2022 Approved STEVEN BACK
Insulation 2/24/2022 Partial Approval STEVEN BACK
Interior/Exterior Lathing 2/24/2022 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 3/3/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/3/2022 Approved STEVEN BACK
Insulation 3/3/2022 Approved STEVEN BACK
Drywall Nailing 3/9/2022 Approved JESUS PINEDA
ELECTRICAL-Final 5/3/2022 Approved STEVEN BACK
Final 5/3/2022 Corrections Issued STEVEN BACK
Gas Test 5/3/2022 Approved STEVEN BACK
Green Building Final 5/3/2022 Approved STEVEN BACK
HVAC-Final 5/3/2022 Approved STEVEN BACK
PLUMBING-Final 5/3/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 5/3/2022 Approved STEVEN BACK
Final 5/11/2022 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved STEVEN BACK