9022 N TAMPA AVE EV 91324
Certificate Information: 9022 N TAMPA AVE EV 91324
- Application / Permit
- 21016-20000-21947
- Plan Check / Job No.
- B21VN11319
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Shopping Center
- Work Description
- ePlan. Re-stripe & install EVCS [24 Tesla Superchargers] at existing surface parking lot of a retail shopping center
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 12/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | PRANITA SHAH |
| Corrections Issued | 10/26/2021 | PRANITA SHAH |
| Quality Review Completed | 11/2/2021 | MINYE PAK |
| Applicant returned to address corrections | 1/19/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 2/1/2022 | PRANITA SHAH |
| Plan Check Approved | 3/23/2022 | PRANITA SHAH |
| Issued | 4/26/2022 | APPLICANT |
| TCO Issued (Expire Date: 05-27-2023) | 11/28/2022 | RICKEY JACKSON |
| CofO in Progress | 12/21/2022 | DEANDRE HOFFMAN |
| CofO Issued | 12/22/2022 | JEFFREY DURAN |
| Permit Finaled | 12/22/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 2/26/2022 | SHINE LIN |
| ZA Case | Cleared | 3/22/2022 | STEVEN WECHSLER |
Contact Information
| No Data Available. |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/5/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 7/5/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 7/7/2022 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 7/8/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Reinf. Concrete | 7/11/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 7/12/2022 | Conditional Approval | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 7/26/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Piling/Pier/Caisson | 7/26/2022 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 7/29/2022 | Partial Inspection | JEFFREY FULTON |
| Final | 11/3/2022 | Off-Hour Fees Due | |
| Reinforced Masonry Frame | 11/3/2022 | No Result Entered | GARY EWELL |
| Reinforced Masonry Frame | 11/3/2022 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | No Result Entered | GARY EWELL |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | Off-Hour Fees Due | |
| Smoke Detectors | 11/3/2022 | No Result Entered | GARY EWELL |
| Smoke Detectors | 11/3/2022 | Off-Hour Fees Due | |
| Final | 11/18/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Reinforced Masonry Frame | 11/18/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Not Ready | DEANDRE HOFFMAN |
| Pre-Inspection | 11/22/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Final | 11/23/2022 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 12/16/2022 | Partial Inspection | DEANDRE HOFFMAN |
| Reinforced Masonry Frame | 12/16/2022 | Approved | DEANDRE HOFFMAN |
| Final | 12/21/2022 | OK to Issue CofO | DEANDRE HOFFMAN |