7458 N SHOUP AVE 91307

Certificate Information: 7458 N SHOUP AVE 91307

Application / Permit
21016-20000-21868
Plan Check / Job No.
B21VN11266
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU conversion. CONVERTING EXISTING DEATTACHED GARAGE ( TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WOOD FRAME DESIGN.
Permit Issued
Issued on 9/28/2021
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2021 APPLICANT
Assigned to Plan Check Engineer 8/22/2021 ZAW HAN
Corrections Issued 8/23/2021 ZAW HAN
Plan Check Approved 8/25/2021 ZAW HAN
Issued 9/28/2021 APPLICANT
CofO in Progress 1/27/2022 PETER FOLLING
Permit Finaled 2/17/2022 RONALD MYRICK
CofO Issued 2/17/2022 RONALD MYRICK
Permit Finaled 2/17/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 8/23/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/23/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 8/23/2021 GABRIEL ROBLES
Sewer availability Cleared 8/23/2021 GABRIEL ROBLES

Contact Information

Contractor Dotz Inc; Lic. No.: 1033830-B 17321 MURPHY AVENUE #240      IRVINE, CA 92614

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 10/4/2021 Approved DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 10/18/2021 Approved DAVID STEPANYAN
HVAC-Rough 11/9/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 11/9/2021 Approved DAVID STEPANYAN
Underground Mechanical 11/9/2021 Partial Approval DAVID STEPANYAN
ELECTRICAL-Rough 11/22/2021 Approved DAVID STEPANYAN
HVAC-Rough 11/22/2021 Partial Approval DAVID STEPANYAN
Insulation 11/22/2021 Not Ready for Inspection DAVID STEPANYAN
Interior/Exterior Lathing 11/22/2021 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 11/30/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Approved VINCENT HANLEY
Green Building Rough 11/30/2021 Approved VINCENT HANLEY
Insulation 11/30/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/30/2021 Partial Approval VINCENT HANLEY
Drywall Nailing 12/6/2021 Not Ready for Inspection JESUS PINEDA
Interior/Exterior Lathing 12/6/2021 Approved JESUS PINEDA
Shower Pan 12/6/2021 Approved JESUS PINEDA
Drywall Nailing 12/13/2021 Approved JAVIER RAMOS JR
Final 1/10/2022 Corrections Issued PETER FOLLING
Green Building Final 1/10/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 1/10/2022 SGSOV Not Ready PETER FOLLING
Smoke Detectors 1/10/2022 Approved PETER FOLLING
Final 1/19/2022 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 1/19/2022 SGSOV Approved STEVEN BACK
Final 1/26/2022 OK to Issue CofO PETER FOLLING