7458 N SHOUP AVE 91307
Certificate Information: 7458 N SHOUP AVE 91307
- Application / Permit
- 21016-20000-21868
- Plan Check / Job No.
- B21VN11266
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU conversion. CONVERTING EXISTING DEATTACHED GARAGE ( TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WOOD FRAME DESIGN.
- Permit Issued
- Issued on 9/28/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2021 | ZAW HAN |
| Corrections Issued | 8/23/2021 | ZAW HAN |
| Plan Check Approved | 8/25/2021 | ZAW HAN |
| Issued | 9/28/2021 | APPLICANT |
| CofO in Progress | 1/27/2022 | PETER FOLLING |
| Permit Finaled | 2/17/2022 | RONALD MYRICK |
| CofO Issued | 2/17/2022 | RONALD MYRICK |
| Permit Finaled | 2/17/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/23/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/23/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | 17321 MURPHY AVENUE #240 IRVINE, CA 92614 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/4/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 10/4/2021 | Approved | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 10/18/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 11/9/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 11/9/2021 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 11/9/2021 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 11/22/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 11/22/2021 | Partial Approval | DAVID STEPANYAN |
| Insulation | 11/22/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Interior/Exterior Lathing | 11/22/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 11/30/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 11/30/2021 | Approved | VINCENT HANLEY |
| Insulation | 11/30/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/30/2021 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 12/6/2021 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 12/6/2021 | Approved | JESUS PINEDA |
| Shower Pan | 12/6/2021 | Approved | JESUS PINEDA |
| Drywall Nailing | 12/13/2021 | Approved | JAVIER RAMOS JR |
| Final | 1/10/2022 | Corrections Issued | PETER FOLLING |
| Green Building Final | 1/10/2022 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 1/10/2022 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 1/10/2022 | Approved | PETER FOLLING |
| Final | 1/19/2022 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 1/19/2022 | SGSOV Approved | STEVEN BACK |
| Final | 1/26/2022 | OK to Issue CofO | PETER FOLLING |