6722 N ST CLAIR AVE 91606
Certificate Information: 6722 N ST CLAIR AVE 91606
- Application / Permit
- 21016-20000-21862
- Plan Check / Job No.
- B21VN11261
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Conversion of an (E) detached 2-car garage into an ADU per state law GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 4/30/2022
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | HELEN NGUYEN |
| Corrections Issued | 9/3/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/8/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/18/2022 | HELEN NGUYEN |
| Plan Check Approved | 3/16/2022 | FARSHAD ALIMOHAMADI |
| Issued | 4/30/2022 | APPLICANT |
| CofO in Progress | 9/21/2022 | RAFAEL CORTES |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
| CofO Issued | 10/15/2022 | MICHAEL SMITH |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/24/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/24/2021 | CARLOS AGUILERA |
| Historic Resource Verification | Cleared | 2/22/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 2/24/2022 | GRACIELA ACOSTA |
Contact Information
| Contractor | Zepeda'S Construction; Lic. No.: 868625-B | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/10/2022 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 6/29/2022 | Approved | RAFAEL CORTES |
| ELECTRICAL-Rough | 7/22/2022 | Corrections Issued | RAFAEL CORTES |
| Gas Test | 7/22/2022 | Partial Approval | RAFAEL CORTES |
| HVAC-Rough | 7/22/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Rough | 7/22/2022 | Approved | RAFAEL CORTES |
| ELECTRICAL-Rough | 7/29/2022 | Approved | RAFAEL CORTES |
| Wood Frame | 7/29/2022 | Approved | RAFAEL CORTES |
| Drywall Nailing | 8/8/2022 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 8/8/2022 | Approved | RAFAEL CORTES |
| Shower Pan | 8/8/2022 | Approved | RAFAEL CORTES |
| BUILDING-Rough-Frame | 9/6/2022 | Approved | RAFAEL CORTES |
| ELECTRICAL-Final | 9/6/2022 | Approved | RAFAEL CORTES |
| Final | 9/6/2022 | Corrections Issued | RAFAEL CORTES |
| HVAC-Final | 9/6/2022 | Approved | RAFAEL CORTES |
| MERV13>=Final | 9/6/2022 | Approved | RAFAEL CORTES |
| MERV13>=Rough | 9/6/2022 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 9/6/2022 | Approved | RAFAEL CORTES |
| ELECTRICAL-Final | 9/21/2022 | Approved | RAFAEL CORTES |
| Final | 9/21/2022 | OK to Issue CofO | RAFAEL CORTES |
| PLUMBING-Final | 9/21/2022 | Approved | RAFAEL CORTES |