4315 S BEETHOVEN ST 90066
Certificate Information: 4315 S BEETHOVEN ST 90066
- Application / Permit
- 21016-20000-21827
- Plan Check / Job No.
- B21VN11250
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTERIOR AND INTERIOR REMODEL TO THE (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 9/23/2021
- Issuing Office
- Current Status
- Issued on 9/23/2021
Permit Application Status History
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | COLIN LOREDO |
| Corrections Issued | 8/22/2021 | COLIN LOREDO |
| Plan Check Approved | 9/14/2021 | COLIN LOREDO |
| Building Plans Picked Up | 9/15/2021 | APPLICANT |
| Issued | 9/23/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/3/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2021 | DINAH GARIN |
Contact Information
| Contractor | Royal Globe Construction Corporation; Lic. No.: 1049671-B | 5967 W 3RD ST STE 370 LOS ANGELES, CA 90036 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/10/2021 | Approved | ENRIQUE MIRELES |
| Deputy Steel/Welding | 12/3/2021 | Approved | ENRIQUE MIRELES |
| Structural Steel Frame | 12/17/2021 | Corrections Issued | ENRIQUE MIRELES |
| Structural Steel Frame | 12/21/2021 | Partial Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2021 | Corrections Issued | ENRIQUE MIRELES |
| Structural Steel Frame | 12/29/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 1/26/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/11/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/7/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/10/2022 | Approved | KENNETH NAGLE |
| Shower Pan | 3/24/2022 | Conditional Approval | PATRICK QUALEY |
| Interior/Exterior Lathing | 4/14/2022 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 5/2/2022 | Corrections Issued | PATRICK QUALEY |
| ELECTRICAL-Rough | 5/2/2022 | Approved | PATRICK QUALEY |
| Interior/Exterior Lathing | 5/5/2022 | Partial Approval | RYAN SALAZAR |
| Insulation | 5/26/2022 | Corrections Issued | PATRICK QUALEY |
| Deputy Wood Construction | 6/27/2022 | No Access for Inspection | PATRICK QUALEY |
| Wood Frame | 6/29/2022 | Corrections Issued | PATRICK QUALEY |
| Deputy Drilled-In Anchors | 7/15/2022 | No Access for Inspection | PATRICK QUALEY |
| HVAC-Rough | 7/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Wood Frame | 7/15/2022 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 7/19/2022 | Partial Inspection | PATRICK QUALEY |
| Insulation | 8/4/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 8/18/2022 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 8/18/2022 | Conditional Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/25/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 8/25/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/25/2022 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 8/25/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Drywall Nailing | 1/4/2023 | Approved | JESUS RODRIGUEZ |
| Final | 1/5/2023 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 1/5/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Special/Order Compliance | 1/24/2023 | Corrections Issued | JESUS RODRIGUEZ |