6618 N LONGRIDGE AVE 91401

Certificate Information: 6618 N LONGRIDGE AVE 91401

Application / Permit
21016-20000-21693
Plan Check / Job No.
B21VN11184
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of an (E) storage and hobby room into an ADU per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 11/9/2021
Issuing Office
Current Status
CofO Issued on 6/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2021 APPLICANT
Assigned to Plan Check Engineer 9/22/2021 HELEN NGUYEN
Corrections Issued 9/24/2021 HELEN NGUYEN
Applicant returned to address corrections 10/19/2021 HELEN NGUYEN
Plan Check Approved 11/1/2021 HELEN NGUYEN
Issued 11/9/2021 APPLICANT
CofO in Progress 3/8/2022 CHRISTOPHE COCHRAN
CofO Issued 6/20/2022 MICHAEL SMITH
Permit Finaled 6/20/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/6/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 10/6/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 10/7/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/3/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/10/2021 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 12/10/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 12/10/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Gas Test 12/15/2021 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 12/15/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Sewer 12/15/2021 Approved CHRISTOPHE COCHRAN
Underground Mechanical 12/15/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/27/2021 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 12/27/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 12/27/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/5/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 1/5/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/11/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 1/11/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/11/2022 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 1/11/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 1/13/2022 Approved CHRISTOPHE COCHRAN
Insulation 1/13/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/13/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/18/2022 Approved JACK KARGODORIAN
Drywall Nailing 1/20/2022 Approved ASHLEY THOMPSON
Final 2/25/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 2/25/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 2/25/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 2/25/2022 Approved CHRISTOPHE COCHRAN
Final 3/8/2022 OK to Issue CofO CHRISTOPHE COCHRAN