2920 S MILITARY AVE 90064
Certificate Information: 2920 S MILITARY AVE 90064
- Application / Permit
- 21016-20000-21517
- Plan Check / Job No.
- B21VN11116
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 34' X 18' DETACHED GARAGE/STORAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 11/22/2021
- Issuing Office
- Current Status
- CofO Issued on 2/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 8/29/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 11/21/2021 | GURUNATH NESARAJAH |
| Issued | 11/22/2021 | APPLICANT |
| Building Plans Picked Up | 11/24/2021 | APPLICANT |
| CofO in Progress | 2/4/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 2/18/2022 | DANIEL ORRANTE |
| CofO Issued | 2/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2021 | RAYMOND MUGAMBWA |
| Sewer availability | Cleared | 9/1/2021 | RAYMOND MUGAMBWA |
| Specific Plan | Cleared | 9/1/2021 | DYLAN SITTIG |
| Specific Plan | Cleared | 9/9/2021 | VALERIA CEJA |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2021 | RAYMOND MUGAMBWA |
| Grading Pre-Inspection | Cleared | 10/13/2021 | BRIAN MILLER |
| Construction near power lines | Cleared | 11/10/2021 | TINA MIRANDA |
Contact Information
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | 21204 VANOWEN STREET CANOGA PARK, CA 91303 |
| Engineer | Ehat,, Frederick P; Lic. No.: C30383 | 34 OPHIR DR DURANGO, CO 81301 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/29/2021 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 11/29/2021 | Partial Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 11/30/2021 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Approved | JOHNNY MIRANDA |
| Insulation | 12/7/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/7/2021 | Approved | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 12/7/2021 | Corrections Issued | JOHNNY MIRANDA |
| Insulation | 12/10/2021 | Conditional Approval | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 12/10/2021 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 12/15/2021 | Not Ready for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 12/15/2021 | Not Ready for Inspection | KRISTEN CAUSEY |
| Shower Pan | 12/15/2021 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 12/17/2021 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/17/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 12/21/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/21/2021 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/27/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/31/2022 | Approved | JOHNNY MIRANDA |
| Final | 1/31/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 1/31/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 1/31/2022 | Approved | JOHNNY MIRANDA |
| MERV13>=Final | 1/31/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 1/31/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 1/31/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 2/3/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 2/3/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 2/3/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 2/3/2022 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Final | 2/3/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 2/3/2022 | Approved | OGANES TARAKHCHYAN |