3004 1/2 W VERNON AVE 90008
Certificate Information: 3004 1/2 W VERNON AVE 90008
- Application / Permit
- 21016-20000-21484
- Plan Check / Job No.
- B21VN11070
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 34'-9" PORTION OF (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/13/2022
- Issuing Office
- Current Status
- Issued on 5/13/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/29/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/27/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 3/10/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Issued | 5/13/2022 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/29/2021 | RICHARD BRINSON |
| Community Plan Implem. Overlay | Cleared | 9/30/2021 | KYLE WINSTON |
| ZI | Cleared | 9/30/2021 | KYLE WINSTON |
| Address approval | Cleared | 10/27/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 10/27/2021 | STEVE MELGAR |
| Construction near power lines | Cleared | 1/28/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2022 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Mario Alberto; Lic. No.: C89006 | 43023 40TH ST WEST LANCASTER, CA 93536 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/12/2022 | Approved | RUSSELL BONVOULOIR |
| Special/Order Compliance | 5/2/2023 | Approved | ALAN MORELOS |
| Pre-Inspection | 5/15/2024 | Conditional Approval | DARRYL ARNOLD |
| Pre-Inspection | 5/21/2024 | Partial Inspection | ANTHONY EGSON |
| Pre-Inspection | 9/25/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/25/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/7/2025 | Approved | LUIS CASTRO |
| Special/Order Compliance | 3/17/2025 | Corrections Issued | LUIS CASTRO |
| Special/Order Compliance | 3/25/2025 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 4/30/2025 | Corrections Issued | LUIS CASTRO |
| Special/Order Compliance | 1/21/2026 | Partial Approval | LUIS CASTRO |