9911 N LEMONA AVE 91345
Certificate Information: 9911 N LEMONA AVE 91345
- Application / Permit
- 21016-20000-21479
- Plan Check / Job No.
- B21VN11062
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/11/2021
- Issuing Office
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2021 | COLIN LOREDO |
| Corrections Issued | 9/15/2021 | COLIN LOREDO |
| Building Plans Picked Up | 9/20/2021 | APPLICANT |
| Plan Check Approved | 10/7/2021 | COLIN LOREDO |
| Issued | 10/11/2021 | APPLICANT |
| CofO in Progress | 1/24/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 2/7/2024 | RUBEN SALAS |
| CofO Issued | 2/7/2024 | RUBEN SALAS |
| Permit Finaled | 2/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/17/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/6/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/13/2023 | Not Ready for Inspection | ROBERT GOLD |
| ELECTRICAL-Rough | 7/13/2023 | Not Ready for Inspection | ROBERT GOLD |
| Green Building Rough | 7/13/2023 | Not Ready for Inspection | ROBERT GOLD |
| PLUMBING-Rough | 7/13/2023 | Partial Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 7/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 7/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/2/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/2/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/2/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 8/2/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 8/8/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/8/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/10/2023 | Partial Approval | DAVID MATSON |
| Insulation | 8/10/2023 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 8/10/2023 | Partial Approval | DAVID MATSON |
| Drywall Nailing | 8/21/2023 | Conditional Approval | JENNIFER RABUCHIN |
| Green Building Rough | 8/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 9/11/2023 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 9/19/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/27/2023 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/29/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 9/29/2023 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/31/2023 | Corrections Issued | ROBERT GOLD |
| HVAC-Final | 10/31/2023 | Approved | ROBERT GOLD |
| PLUMBING-Final | 10/31/2023 | Corrections Issued | ROBERT GOLD |
| ELECTRICAL-Final | 11/7/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 11/7/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/17/2023 | Approved | JENNIFER RABUCHIN |
| Gas Test | 11/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 11/21/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/30/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/30/2023 | Approved | JENNIFER RABUCHIN |
| Final | 11/30/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 11/30/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 11/30/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 11/30/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 11/30/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/25/2024 | Approved | JENNIFER RABUCHIN |
| Final | 1/25/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 1/25/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/25/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Approved | JENNIFER RABUCHIN |