9911 N LEMONA AVE 91345

Certificate Information: 9911 N LEMONA AVE 91345

Application / Permit
21016-20000-21479
Plan Check / Job No.
B21VN11062
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/11/2021
Issuing Office
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/14/2021 COLIN LOREDO
Corrections Issued 9/15/2021 COLIN LOREDO
Building Plans Picked Up 9/20/2021 APPLICANT
Plan Check Approved 10/7/2021 COLIN LOREDO
Issued 10/11/2021 APPLICANT
CofO in Progress 1/24/2024 JENNIFER RABUCHIN
Permit Finaled 2/7/2024 RUBEN SALAS
CofO Issued 2/7/2024 RUBEN SALAS
Permit Finaled 2/7/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/17/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/17/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/17/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/26/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 6/6/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/13/2023 Not Ready for Inspection ROBERT GOLD
ELECTRICAL-Rough 7/13/2023 Not Ready for Inspection ROBERT GOLD
Green Building Rough 7/13/2023 Not Ready for Inspection ROBERT GOLD
PLUMBING-Rough 7/13/2023 Partial Approval ROBERT GOLD
ELECTRICAL-Rough 7/21/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 7/21/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 7/26/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 7/26/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 7/26/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 8/2/2023 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 8/2/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/2/2023 Approved JENNIFER RABUCHIN
Underground Mechanical 8/2/2023 Corrections Issued JENNIFER RABUCHIN
Insulation 8/8/2023 No Access for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 8/8/2023 No Access for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 8/10/2023 Partial Approval DAVID MATSON
Insulation 8/10/2023 Approved DAVID MATSON
Interior/Exterior Lathing 8/10/2023 Partial Approval DAVID MATSON
Drywall Nailing 8/21/2023 Conditional Approval JENNIFER RABUCHIN
Green Building Rough 8/21/2023 Corrections Issued JENNIFER RABUCHIN
Shower Pan 9/11/2023 Approved MISAEL ESPARZA
Underground Mechanical 9/19/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 9/27/2023 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 9/29/2023 Approved MICHEL ABAJAN
Underground Mechanical 9/29/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 10/31/2023 Corrections Issued ROBERT GOLD
HVAC-Final 10/31/2023 Approved ROBERT GOLD
PLUMBING-Final 10/31/2023 Corrections Issued ROBERT GOLD
ELECTRICAL-Final 11/7/2023 Corrections Issued JENNIFER RABUCHIN
Final 11/7/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 11/7/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/17/2023 Approved JENNIFER RABUCHIN
Gas Test 11/17/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/17/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 11/21/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Not Ready JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/30/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 11/30/2023 Approved JENNIFER RABUCHIN
Final 11/30/2023 Partial Approval JENNIFER RABUCHIN
Green Building Final 11/30/2023 Approved JENNIFER RABUCHIN
MERV13>=Final 11/30/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 11/30/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/30/2023 Approved JENNIFER RABUCHIN
Smoke Detectors 11/30/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/25/2024 Approved JENNIFER RABUCHIN
Final 1/25/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 1/25/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/25/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/25/2024 SGSOV Approved JENNIFER RABUCHIN