6899-6901 N MATILIJA AVE 91405
Certificate Information: 6899-6901 N MATILIJA AVE 91405
- Application / Permit
- 21016-20000-21141
- Plan Check / Job No.
- B21VN10844
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 16'-2" X 23'-11.75" (359 SF) PORTION OF SFD TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/21/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2021 | RAPHAEL ROSAS |
| Corrections Issued | 10/3/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 2/24/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| Issued | 6/21/2024 | APPLICANT |
| CofO Issued | 11/21/2025 | RUBEN SALAS |
| Permit Finaled | 11/21/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/6/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/13/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 3/14/2025 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 3/14/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 3/14/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 4/16/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 5/6/2025 | Approved | RYAN SALAZAR |
| Insulation | 5/6/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/6/2025 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 5/6/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 5/15/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/15/2025 | Approved | RYAN SALAZAR |
| Final | 10/2/2025 | Corrections Issued | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 10/2/2025 | Approved | RYAN SALAZAR |
| Final | 11/13/2025 | Partial Approval | RYAN SALAZAR |