7435 N NITA AVE 91303

Certificate Information: 7435 N NITA AVE 91303

Application / Permit
21016-20000-20969
Plan Check / Job No.
B21VN10739
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convert existing detached 2-car Garage into an Accessory Dwelling Unit per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 1/19/2022
Issuing Office
Current Status
CofO Issued on 12/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2021 APPLICANT
Assigned to Plan Check Engineer 8/18/2021 MONICA RAMIREZ
Corrections Issued 8/19/2021 MONICA RAMIREZ
Applicant returned to address corrections 10/15/2021 MONICA RAMIREZ
Applicant returned to address corrections 12/6/2021 MONICA RAMIREZ
Plan Check Approved 12/23/2021 JOE VO
Issued 1/19/2022 APPLICANT
CofO in Progress 12/15/2022 KRISTEN BEVERIDGE
Permit Finaled 12/19/2022 JOHN JANSON
CofO Issued 12/19/2022 JOHN JANSON
Permit Finaled 12/19/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/14/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/14/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/15/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Judd,, Shane Dennis; Lic. No.: NA70991       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/23/2022 Conditional Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 6/22/2022 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/24/2022 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 6/24/2022 Approved PETER FOLLING
Green Building Rough 6/24/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 6/24/2022 Partial Approval PETER FOLLING
Pre-Inspection 6/24/2022 Not Ready for Inspection PETER FOLLING
Sewer 6/24/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 7/13/2022 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 7/13/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/25/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/25/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 7/25/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/27/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 7/27/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 7/27/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/5/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 8/5/2022 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/8/2022 Approved JUSTIN HAWLEY
Green Building Rough 8/8/2022 Approved JUSTIN HAWLEY
Insulation 8/8/2022 Approved JUSTIN HAWLEY
Drywall Nailing 8/17/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 11/15/2022 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Final 11/15/2022 Corrections Issued CHRIS CHRISTENSEN
Underground Mechanical 11/15/2022 Conditional Approval CHRIS CHRISTENSEN
Final 11/29/2022 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 11/29/2022 Not Ready for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Not Ready KRISTEN CAUSEY
Smoke Detectors 11/29/2022 Not Ready for Inspection KRISTEN CAUSEY
Final 12/5/2022 Corrections Issued CHRIS CHRISTENSEN
Service/Power Release 12/5/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Special/Order Compliance 12/5/2022 Partial Inspection KRISTEN CAUSEY
Final 12/13/2022 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 12/13/2022 Not Ready for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 12/13/2022 Not Ready for Inspection KRISTEN CAUSEY
Final 12/14/2022 OK to Issue CofO KRISTEN CAUSEY
Green Building Final 12/14/2022 Approved KRISTEN CAUSEY
Smoke Detectors 12/14/2022 Approved KRISTEN CAUSEY