6650 N CEDROS AVE 91405
Certificate Information: 6650 N CEDROS AVE 91405
- Application / Permit
- 21016-20000-20773
- Plan Check / Job No.
- B21VN10646
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/20/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 9/1/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 9/2/2021 | APPLICANT |
| Issued | 9/13/2021 | APPLICANT |
| CofO in Progress | 4/27/2022 | RICHARD DOCKUS |
| Permit Finaled | 5/2/2022 | RONALD MYRICK |
| CofO Issued | 5/2/2022 | RONALD MYRICK |
| Permit Finaled | 5/2/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/24/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 8/26/2021 | DANG NGUYEN |
| ZA Case | Cleared | 8/26/2021 | DANG NGUYEN |
| ZA Case | Cleared | 8/26/2021 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/26/2021 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/10/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/10/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/6/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 12/6/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 12/6/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 12/6/2021 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 12/9/2021 | No Access for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 12/9/2021 | No Access for Inspection | RICHARD DOCKUS |
| Rough-Elec/Plmb/HVAC | 1/5/2022 | Approved | MICHEL ABAJAN |
| Insulation | 1/11/2022 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Rough | 1/11/2022 | Not Ready for Inspection | ALAN MORELOS |
| Insulation | 1/21/2022 | Approved | RICHARD DOCKUS |
| Gas Test | 1/26/2022 | Partial Approval | ALAN MORELOS |
| Interior/Exterior Lathing | 1/26/2022 | Partial Approval | ALAN MORELOS |
| Underground Mechanical | 1/26/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 2/3/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 2/3/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 4/11/2022 | Approved | MICHAEL TEMPLE |
| Final | 4/11/2022 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 4/11/2022 | Approved | MICHAEL TEMPLE |
| Green Building Rough | 4/11/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Rough | 4/11/2022 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 4/11/2022 | SGSOV Approved | MICHAEL TEMPLE |
| Smoke Detectors | 4/11/2022 | Approved | MICHAEL TEMPLE |
| Final | 4/15/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 4/20/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 4/26/2022 | OK to Issue CofO | RICHARD DOCKUS |