12726 W PAXTON ST 91331

Certificate Information: 12726 W PAXTON ST 91331

Application / Permit
21016-20000-20764
Plan Check / Job No.
B21VN10637
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 22'-6" x 21'-6" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). "COMPLY WITH DEPARTMENT ORDER effective date 07/06/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 2/7/2022
Issuing Office
Current Status
CofO Issued on 5/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 8/24/2021 SARKIS HARABEDIAN
Corrections Issued 8/26/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 9/29/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 12/22/2021 SARKIS HARABEDIAN
Plan Check Approved 1/17/2022 SARKIS HARABEDIAN
Building Plans Picked Up 1/19/2022 APPLICANT
Issued 2/7/2022 APPLICANT
CofO in Progress 12/20/2023 MARK VAN SLOOTEN
CofO Issued 5/30/2025 DAVID JAMES
Permit Finaled 5/30/2025 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 9/7/2021 GABRIEL ROBLES
Sewer availability Cleared 9/7/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/21/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Ghavimi,, Rassoul Daneshvar; Lic. No.: C48282 7007 SHADETREE LANE      WEST HILLS, CA 91307

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/30/2022 Approved JASON BRANNON
Footing/Foundation/Slab 4/1/2022 Approved JASON BRANNON
BUILDING-Rough-Frame 4/8/2022 Corrections Issued JOHN STEPHENS
Green Building Rough 4/8/2022 Not Ready for Inspection JOHN STEPHENS
MERV13>=Rough 4/8/2022 Not Ready for Inspection JOHN STEPHENS
BUILDING-Rough-Frame 5/10/2022 Partial Approval JOHN STEPHENS
ELECTRICAL-Rough 5/10/2022 Partial Approval JOHN STEPHENS
Green Building Rough 5/10/2022 Partial Approval JOHN STEPHENS
MERV13>=Rough 5/10/2022 Partial Approval JOHN STEPHENS
Insulation 5/19/2022 Approved JOHN STEPHENS
PLUMBING-Rough 5/19/2022 Corrections Issued JOHN STEPHENS
Drywall Nailing 6/8/2022 Approved EMIL ALEXANDRIAN
PLUMBING-Rough 6/8/2022 Approved EMIL ALEXANDRIAN
ELECTRICAL-Final 10/28/2022 Not Ready for Inspection JASON BRANNON
ELECTRICAL-Rough 11/15/2022 Approved JASON BRANNON
BUILDING-Rough-Frame 12/22/2022 Not Ready for Inspection JASON BRANNON
Final 12/22/2022 Not Ready for Inspection JASON BRANNON
Green Building Final 12/22/2022 Not Ready for Inspection JASON BRANNON
Green Building Rough 12/22/2022 Approved JASON BRANNON
MERV13>=Final 12/22/2022 Not Ready for Inspection JASON BRANNON
MERV13>=Rough 12/22/2022 Not Ready for Inspection JASON BRANNON
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Not Ready JASON BRANNON
Smoke Detectors 12/22/2022 Approved JASON BRANNON
BUILDING-Rough-Frame 1/4/2023 Partial Approval JASON BRANNON
Final 1/4/2023 Not Ready for Inspection JASON BRANNON
Green Building Final 1/4/2023 Not Ready for Inspection JASON BRANNON
MERV13>=Final 1/4/2023 Not Ready for Inspection JASON BRANNON
MERV13>=Rough 1/4/2023 Not Ready for Inspection JASON BRANNON
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Not Ready JASON BRANNON
BUILDING-Rough-Frame 1/24/2023 Approved LEO MILBAUER
Final 1/24/2023 Conditional Approval LEO MILBAUER
Green Building Final 1/24/2023 Approved LEO MILBAUER
MERV13>=Final 1/24/2023 Approved LEO MILBAUER
MERV13>=Rough 1/24/2023 Approved LEO MILBAUER
SGSOV-Seismic Gas S/O Valve 1/24/2023 SGSOV Approved LEO MILBAUER
Final 8/17/2023 Corrections Issued PIERRE VEGA
Gas Test 9/13/2023 Approved PIERRE VEGA
PLUMBING-Final 9/13/2023 Not Ready for Inspection PIERRE VEGA
Gas Test 9/20/2023 Approved PIERRE VEGA
PLUMBING-Final 9/20/2023 Not Ready for Inspection PIERRE VEGA
Gas Test 9/27/2023 Partial Approval PIERRE VEGA
PLUMBING-Final 9/27/2023 Not Ready for Inspection PIERRE VEGA
Underground Mechanical 9/27/2023 Partial Approval PIERRE VEGA
Final 11/8/2023 Partial Approval PIERRE VEGA
PLUMBING-Final 11/8/2023 Not Ready for Inspection PIERRE VEGA
Final 11/28/2023 Corrections Issued MARK VAN SLOOTEN
PLUMBING-Final 11/28/2023 Corrections Issued MARK VAN SLOOTEN
Final 12/19/2023 Conditional Approval MARK VAN SLOOTEN
PLUMBING-Final 12/19/2023 Approved MARK VAN SLOOTEN
Final 8/30/2024 Conditional Approval MARK VAN SLOOTEN
Final 9/18/2024 Conditional Approval MARK VAN SLOOTEN