9724-9726 N BEACHY AVE 91331
Certificate Information: 9724-9726 N BEACHY AVE 91331
- Application / Permit
- 21016-20000-20651
- Plan Check / Job No.
- B21VN10589
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan. Conversion of an (E) attached rec. room and 2-car garage into an ADU per ordinance 186,481.
- Permit Issued
- Issued on 10/28/2022
- Issuing Office
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2021 | JOSEPH RAFOLS |
| Corrections Issued | 8/16/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/29/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 10/3/2022 | JOSEPH RAFOLS |
| Issued | 10/28/2022 | APPLICANT |
| CofO in Progress | 9/27/2023 | MICHEL ABAJAN |
| CofO Issued | 11/14/2023 | RUBEN SALAS |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/30/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/8/2023 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 5/9/2023 | Conditional Approval | MICHAEL SMITH |
| Pre-Inspection | 5/10/2023 | Partial Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/5/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/5/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/5/2023 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 6/5/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/5/2023 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/8/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/8/2023 | Approved | MICHEL ABAJAN |
| Insulation | 6/14/2023 | Corrections Issued | WILLIAM WREN |
| Shower Pan | 6/14/2023 | Approved | WILLIAM WREN |
| Insulation | 6/16/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 6/16/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 6/20/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/20/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/29/2023 | Approved | MICHEL ABAJAN |
| Final | 8/29/2023 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 8/29/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 8/29/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 8/29/2023 | Approved | MICHEL ABAJAN |
| Final | 9/27/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 9/27/2023 | Approved | MICHEL ABAJAN |