5915 N CAHILL AVE 91356

Certificate Information: 5915 N CAHILL AVE 91356

Application / Permit
21016-20000-20582
Plan Check / Job No.
B21VN10561
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE/ WORKSHOP BUILDING INTO ACCESSORY DWELLING UNIT PER CA. GOV STATE CODE 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 2/22/2022
Issuing Office
Current Status
CofO Issued on 5/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/18/2021 ROSENDO MEDINA
Corrections Issued 8/21/2021 ROSENDO MEDINA
Applicant returned to address corrections 9/27/2021 ROSENDO MEDINA
Applicant returned to address corrections 12/22/2021 ROSENDO MEDINA
Plan Check Approved 2/22/2022 ROSENDO MEDINA
Issued 2/22/2022 APPLICANT
Building Plans Picked Up 2/23/2022 APPLICANT
CofO in Progress 5/3/2022 SEAN HAUPT
Permit Finaled 5/18/2022 MICHAEL SMITH
CofO Issued 5/18/2022 MICHAEL SMITH
Permit Finaled 5/18/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/25/2021 CARLOS AGUILERA
Sewer availability Cleared 8/25/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/19/2021 CARLOS AGUILERA
Construction near power lines Cleared 12/9/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/1/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 3/1/2022 Approved SEAN HAUPT
Underground Mechanical 3/1/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 3/2/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 3/2/2022 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 3/2/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/7/2022 Approved SEAN HAUPT
Green Building Rough 3/7/2022 Not Ready for Inspection SEAN HAUPT
Insulation 3/9/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 3/9/2022 Approved SEAN HAUPT
Shower Pan 3/9/2022 Approved SEAN HAUPT
Drywall Nailing 3/15/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 5/2/2022 Approved SEAN HAUPT
ELECTRICAL-Final 5/2/2022 Approved SEAN HAUPT
Final 5/2/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 5/2/2022 Approved SEAN HAUPT
Green Building Rough 5/2/2022 Approved SEAN HAUPT
HVAC-Final 5/2/2022 Approved SEAN HAUPT
PLUMBING-Final 5/2/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 5/2/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 5/2/2022 Approved SEAN HAUPT