5911 E MERIDIAN ST 90042
Certificate Information: 5911 E MERIDIAN ST 90042
- Application / Permit
- 21016-20000-20460
- Plan Check / Job No.
- B21VN10488
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- FIRE DAMAGE REPAIRES: REMOVE AND REPLACE THE (E) INSULATION, WINDOWS AND DOORS, AND DRYWALL. NO CHANGES TO THE FLOOR AREA, PLOT PLAN, HEIGHT, AND SETBACKS.
- Permit Issued
- Issued on 8/14/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/14/2022
Permit Application Status History
| Submitted | 8/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2021 | COLIN LOREDO |
| Plan Check Approved | 8/9/2021 | COLIN LOREDO |
| Building Plans Picked Up | 8/10/2021 | APPLICANT |
| Issued | 8/14/2021 | APPLICANT |
| Permit Finaled | 9/13/2022 | MARK FERRARI |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Vicsinc.Com; Lic. No.: 1002544-B | P O BOX 950931 MISSION HILLS, CA 91395 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Approved | RAFAEL ESPINOZA |
| Pre-Inspection | 9/20/2021 | Corrections Issued | RAFAEL ESPINOZA |
| Pre-Inspection | 10/21/2021 | Corrections Issued | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 2/15/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 2/15/2022 | Not Ready for Inspection | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 2/22/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 2/22/2022 | Not Ready for Inspection | MARK FERRARI |
| Pre-Inspection | 3/2/2022 | Not Ready for Inspection | MARK FERRARI |
| Insulation | 3/4/2022 | Approved | MARK FERRARI |
| Wood Frame | 3/4/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 3/7/2022 | Partial Approval | MARK FERRARI |
| Wood Frame | 3/7/2022 | Approved | MARK FERRARI |
| Drywall Nailing | 3/8/2022 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 3/8/2022 | Approved | MARK FERRARI |
| Final | 9/13/2022 | Permit Finaled | MARK FERRARI |
| Smoke Detectors | 9/13/2022 | Approved | MARK FERRARI |