7815 N ARCOLA AVE 91352
Certificate Information: 7815 N ARCOLA AVE 91352
- Application / Permit
- 21016-20000-20382
- Plan Check / Job No.
- B21VN10424
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 22' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/14/2021 | RAPHAEL ROSAS |
| Issued | 8/31/2021 | APPLICANT |
| Building Plans Picked Up | 9/1/2021 | APPLICANT |
| CofO in Progress | 10/6/2022 | DAVID ANDERSON |
| Permit Finaled | 3/2/2023 | DANIEL ORRANTE |
| CofO Issued | 3/2/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/2/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/24/2021 | GABRIEL ROBLES |
| Address approval | Cleared | 8/26/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/11/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/11/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 1/11/2022 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Rough | 1/11/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Pre-Inspection | 1/11/2022 | Partial Inspection | MATTHEW NELSON |
| Wood Frame | 1/11/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 1/28/2022 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 1/31/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/31/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 2/3/2022 | Conditional Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 2/4/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/18/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 2/18/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 2/18/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/18/2022 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 2/18/2022 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/3/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 3/3/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 3/3/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/10/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 3/10/2022 | Corrections Issued | WILLIAM WREN |
| HVAC-Rough | 3/10/2022 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 3/10/2022 | Approved | WILLIAM WREN |
| Wood Frame | 3/10/2022 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/14/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 3/14/2022 | Approved | WILLIAM WREN |
| Gas Test | 3/15/2022 | Partial Approval | WILLIAM WREN |
| Underground Mechanical | 3/15/2022 | Approved | WILLIAM WREN |
| Insulation | 3/16/2022 | Approved | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 4/1/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/1/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Shower Pan | 4/1/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/5/2022 | Corrections Issued | WILLIAM WREN |
| Shower Pan | 4/5/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 4/8/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 9/16/2022 | Approved | DAVID ANDERSON |
| Final | 9/16/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 9/16/2022 | Approved | DAVID ANDERSON |
| MERV13>=Final | 9/16/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 9/16/2022 | Approved | DAVID ANDERSON |
| Smoke Detectors | 9/16/2022 | Approved | DAVID ANDERSON |
| Final | 10/5/2022 | OK to Issue CofO | DAVID ANDERSON |