1718 N RODNEY DR 90027
Certificate Information: 1718 N RODNEY DR 90027
- Application / Permit
- 21016-20000-20379
- Plan Check / Job No.
- B21VN10422
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 672 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT. W/ (9'-0"x39'-2"), 323 SQFT ADDITION AND NEW 89 SQFT STORAGE PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Current Status
- CofO Issued on 11/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2021 | LUIS RINCON |
| Corrections Issued | 8/14/2021 | LUIS RINCON |
| Applicant returned to address corrections | 12/10/2021 | LUIS RINCON |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| Issued | 2/17/2022 | APPLICANT |
| CofO in Progress | 10/24/2022 | JOSEPH MCGARRY |
| Permit Finaled | 11/6/2022 | DEROLD HAUFF |
| CofO Issued | 11/6/2022 | DEROLD HAUFF |
| Permit Finaled | 11/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 8/26/2021 | DANG NGUYEN |
| Address approval | Cleared | 8/30/2021 | WALLIE JONG |
| Sewer availability | Cleared | 8/30/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | WALLIE JONG |
| Specific Plan | Cleared | 9/28/2021 | DANALYNN DOMINGUEZ |
| Construction near power lines | Cleared | 12/15/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/6/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/10/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/24/2022 | Approved | STUART CHAPMAN |
| Pre-Inspection | 5/26/2022 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 6/6/2022 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/6/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/17/2022 | Approved | JOSEPH MCGARRY |
| Sewer | 6/17/2022 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 6/30/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/5/2022 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 7/5/2022 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 7/5/2022 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/22/2022 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 7/22/2022 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 7/22/2022 | Approved | JOSEPH MCGARRY |
| Shower Pan | 7/22/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/27/2022 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 7/27/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/11/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 8/11/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/11/2022 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 8/24/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/24/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 9/29/2022 | Approved | JOSEPH MCGARRY |
| Final | 9/29/2022 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 9/29/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 9/29/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 9/29/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/29/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 9/29/2022 | Approved | JOSEPH MCGARRY |
| Final | 10/12/2022 | Corrections Issued | JOSEPH MCGARRY |
| Final | 10/19/2022 | OK to Issue CofO | JOSEPH MCGARRY |