8765 N WINNETKA AVE 91306

Certificate Information: 8765 N WINNETKA AVE 91306

Application / Permit
21016-20000-20316
Plan Check / Job No.
B21VN10403
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA GOV. STATE 65852.2(e)(1)(A). WORK PER DESIGN.
Permit Issued
Issued on 8/27/2021
Issuing Office
Current Status
CofO Issued on 4/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2021 APPLICANT
Assigned to Plan Check Engineer 8/13/2021 ROSENDO MEDINA
Corrections Issued 8/14/2021 ROSENDO MEDINA
Plan Check Approved 8/27/2021 ROSENDO MEDINA
Issued 8/27/2021 APPLICANT
Building Plans Picked Up 8/30/2021 APPLICANT
CofO in Progress 4/11/2022 CHRIS CHRISTENSEN
Permit Finaled 4/19/2022 JOHN JANSON
CofO Issued 4/19/2022 JOHN JANSON
Permit Finaled 4/19/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/18/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/18/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/18/2021 DAGOVERTO GUERRERO

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B 21204 VANOWEN STREET      CANOGA PARK, CA 91303

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/6/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 10/21/2021 Partial Approval STEVEN BACK
ELECTRICAL-Rough 10/28/2021 Corrections Issued DAVID STEPANYAN
HVAC-Rough 10/28/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 10/28/2021 Partial Approval DAVID STEPANYAN
Underground Mechanical 10/28/2021 Corrections Issued DAVID STEPANYAN
Rough-Elec/Plmb/HVAC 11/2/2021 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 11/9/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 11/9/2021 Partial Approval DAVID STEPANYAN
ELECTRICAL-Rough 11/22/2021 Approved DAVID STEPANYAN
ELECTRICAL-Rough 12/3/2021 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 12/3/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 12/3/2021 Not Ready for Inspection VINCENT HANLEY
Interior/Exterior Lathing 12/10/2021 Approved JEFFREY PARD
Rough-Elec/Plmb/HVAC 12/10/2021 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 12/14/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Rough 12/14/2021 Not Ready for Inspection DAVID STEPANYAN
Interior/Exterior Lathing 12/14/2021 Partial Approval DAVID STEPANYAN
Pre-Inspection 12/14/2021 Partial Inspection DAVID STEPANYAN
Rough-Elec/Plmb/HVAC 12/14/2021 Corrections Issued DAVID STEPANYAN
Wood Frame 12/14/2021 Partial Approval DAVID STEPANYAN
HVAC-Rough 12/21/2021 Partial Approval DAVID STEPANYAN
Interior/Exterior Lathing 12/21/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 12/21/2021 Partial Approval DAVID STEPANYAN
Wood Frame 12/21/2021 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 12/30/2021 Corrections Issued PETER FOLLING
Insulation 12/30/2021 Not Ready for Inspection PETER FOLLING
HVAC-Rough 1/3/2022 Not Ready for Inspection DAVID SANDOVAL
Insulation 1/3/2022 Corrections Issued DAVID SANDOVAL
HVAC-Rough 1/5/2022 Corrections Issued SEAN HAUPT
Insulation 1/5/2022 Corrections Issued SEAN HAUPT
Insulation 1/6/2022 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 1/12/2022 Approved TROY SANDERS
ELECTRICAL-Rough 1/12/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/12/2022 Partial Approval TROY SANDERS
Green Building Rough 1/12/2022 Approved TROY SANDERS
HVAC-Rough 1/12/2022 Approved TROY SANDERS
Insulation 1/12/2022 Approved TROY SANDERS
Interior/Exterior Lathing 1/12/2022 Partial Approval TROY SANDERS
PLUMBING-Rough 1/12/2022 Approved TROY SANDERS
Drywall Nailing 1/18/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 1/18/2022 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Not Ready TROY SANDERS
ELECTRICAL-Final 2/24/2022 Corrections Issued HENRY KIM
Final 2/24/2022 Corrections Issued HENRY KIM
Green Building Final 2/24/2022 Approved HENRY KIM
HVAC-Final 2/24/2022 Corrections Issued HENRY KIM
PLUMBING-Final 2/24/2022 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 2/24/2022 SGSOV Not Ready HENRY KIM
Smoke Detectors 2/24/2022 Corrections Issued HENRY KIM
ELECTRICAL-Final 3/3/2022 Not Ready for Inspection PETER FOLLING
Final 3/3/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Final 3/3/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Final 3/16/2022 Approved CHRIS CHRISTENSEN
Final 3/16/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 3/16/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 3/16/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 3/16/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 3/16/2022 Approved CHRIS CHRISTENSEN
Final 4/5/2022 Corrections Issued CHRIS CHRISTENSEN
Final 4/8/2022 OK to Issue CofO CHRIS CHRISTENSEN