4828 E HUB ST 90042
Certificate Information: 4828 E HUB ST 90042
- Application / Permit
- 21016-20000-20300
- Plan Check / Job No.
- B21VN10383
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 10' X 24' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 10/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/14/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 8/16/2021 | APPLICANT |
| Plan Check Approved | 9/30/2021 | RAPHAEL ROSAS |
| Issued | 10/22/2021 | APPLICANT |
| CofO in Progress | 8/17/2023 | HAMIK HARTOUNIAN |
| CofO Issued | 8/17/2023 | RONALD MYRICK |
| Permit Finaled | 8/17/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/27/2021 | CECILIO NAVARRO |
| Street Frontage | Cleared | 8/27/2021 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 9/13/2021 | TIMOTHY POWELL |
Contact Information
| Contractor | Yor Construction And Investments Inc; Lic. No.: 978430-B | 12135 MIRANDA ST VALLEY VILLAGE, CA 91607 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/22/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 11/23/2021 | Conditional Approval | JUSTIN HAWLEY |
| Underground Mechanical | 12/1/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/6/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/3/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/19/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/14/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/14/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/14/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 4/14/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/19/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/19/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 5/19/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/19/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 5/19/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/24/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 5/24/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/27/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/3/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 6/9/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/9/2022 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 6/9/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/11/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Shower Pan | 7/11/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/19/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/28/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/28/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 8/1/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 12/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 12/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Gas Company | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 2/9/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 2/9/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/9/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 5/26/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 5/26/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/26/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 8/8/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 8/8/2023 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/8/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 8/17/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |