5576 W 83RD ST 90045

Certificate Information: 5576 W 83RD ST 90045

Application / Permit
21016-20000-20298
Plan Check / Job No.
B21VN10379
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 24' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/1/2022
Issuing Office
Current Status
CofO Issued on 9/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2021 APPLICANT
Assigned to Plan Check Engineer 8/27/2021 RAPHAEL ROSAS
Corrections Issued 8/28/2021 RAPHAEL ROSAS
Applicant returned to address corrections 10/12/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/13/2021 RAPHAEL ROSAS
Applicant returned to address corrections 1/24/2022 RAPHAEL ROSAS
Applicant returned to address corrections 2/9/2022 RAPHAEL ROSAS
Plan Check Approved 3/8/2022 RAPHAEL ROSAS
Building Plans Picked Up 3/9/2022 APPLICANT
Issued 4/1/2022 APPLICANT
CofO in Progress 9/15/2022 BOBBY KEY
Permit Finaled 9/22/2022 DANIEL ORRANTE
CofO Issued 9/22/2022 DANIEL ORRANTE
Permit Finaled 9/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

Hold Cleared 8/31/2021 JASON SHEETS
ZA Case Cleared 10/20/2021 LAUREN PADICK
Address approval Cleared 10/25/2021 DENNIS BRAGIN
Grading Pre-Inspection Cleared 10/25/2021 BRIAN MILLER
Sewer availability Cleared 10/25/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 10/26/2021 DENNIS BRAGIN
Construction near power lines Cleared 1/22/2022 RIDWAN HARDY

Contact Information

Contractor Red Stag Construction Company; Lic. No.: 964664-B 9948 SEPULVEDA BLVD #6      MISSION HILLS, CA 91345
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/25/2022 Approved BOBBY KEY
Underground Mechanical 5/25/2022 Partial Approval BOBBY KEY
Sewer 6/1/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 6/6/2022 Partial Approval BOBBY KEY
Underground Mechanical 6/6/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Partial Approval BOBBY KEY
ELECTRICAL-Rough 6/24/2022 Approved BOBBY KEY
HVAC-Rough 6/24/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 6/24/2022 Approved BOBBY KEY
Special/Order Compliance 6/24/2022 Corrections Issued RICHARD STEINBACH
BUILDING-Rough-Frame 6/28/2022 Partial Approval BOBBY KEY
HVAC-Rough 6/28/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 7/6/2022 Partial Approval STEPHANIE SWANSON
Green Building Rough 7/6/2022 Approved STEPHANIE SWANSON
Insulation 7/6/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 7/6/2022 Partial Approval STEPHANIE SWANSON
Insulation 7/8/2022 Approved BOBBY KEY
Underground Mechanical 7/8/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 7/12/2022 Approved BOBBY KEY
Interior/Exterior Lathing 7/12/2022 Partial Approval BOBBY KEY
Drywall Nailing 7/15/2022 Approved HERBERT GIRON
Shower Pan 7/15/2022 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 7/20/2022 Approved STEPHANIE SWANSON
Shower Pan 7/20/2022 Approved STEPHANIE SWANSON
Final 9/9/2022 Corrections Issued BOBBY KEY
Green Building Final 9/9/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV Not Ready BOBBY KEY
Smoke Detectors 9/9/2022 Approved BOBBY KEY
Final 9/15/2022 OK to Issue CofO BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Approved BOBBY KEY