6715-6717 N JAMIESON AVE 91335

Certificate Information: 6715-6717 N JAMIESON AVE 91335

Application / Permit
21016-20000-20155
Plan Check / Job No.
B21VN10300
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATTACHED GARAGE INTO JR ACCESSORY DWELLING UNIT WITH SEPARATE LAUNDRY RM PER GCS 65852.2(e)(1)(A) AND 65852.22. SEE COMMENTS.
Permit Issued
Issued on 8/26/2021
Issuing Office
Current Status
CofO Issued on 4/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2021 APPLICANT
Assigned to Plan Check Engineer 8/13/2021 HAYATO TSUCHIYA
Corrections Issued 8/15/2021 HAYATO TSUCHIYA
Plan Check Approved 8/25/2021 HAYATO TSUCHIYA
Issued 8/26/2021 APPLICANT
Building Plans Picked Up 8/26/2021 APPLICANT
CofO in Progress 3/30/2022 WILL MCCONNAUGHY
Permit Finaled 4/29/2022 MICHAEL SMITH
CofO Issued 4/29/2022 MICHAEL SMITH
Permit Finaled 4/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/18/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/18/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/19/2021 DAGOVERTO GUERRERO

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/16/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 11/16/2021 Approved VINCENT HANLEY
PLUMBING-Rough 11/16/2021 Partial Approval VINCENT HANLEY
Sewer 11/16/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/27/2021 Partial Approval VINCENT HANLEY
Gas Test 12/27/2021 Partial Approval VINCENT HANLEY
HVAC-Rough 12/27/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 12/27/2021 Partial Approval VINCENT HANLEY
Wood Frame 12/27/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 1/7/2022 Approved PETER FOLLING
HVAC-Rough 1/7/2022 Not Ready for Inspection PETER FOLLING
Insulation 1/7/2022 Approved PETER FOLLING
PLUMBING-Rough 1/7/2022 Approved PETER FOLLING
Wood Frame 1/7/2022 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 1/11/2022 Approved VINCENT HANLEY
Drywall Nailing 1/11/2022 Approved VINCENT HANLEY
Green Building Rough 1/11/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/11/2022 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 1/25/2022 Approved MORRIS JACKSON
Shower Pan 1/25/2022 Approved MORRIS JACKSON
ELECTRICAL-Final 3/17/2022 Approved VINCENT HANLEY
Final 3/17/2022 Corrections Issued VINCENT HANLEY
Green Building Final 3/17/2022 Approved VINCENT HANLEY
HVAC-Final 3/17/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Final 3/17/2022 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 3/17/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 3/29/2022 Approved VINCENT HANLEY
Final 3/29/2022 OK to Issue CofO VINCENT HANLEY
HVAC-Final 3/29/2022 Approved VINCENT HANLEY
PLUMBING-Final 3/29/2022 Approved VINCENT HANLEY