6457 W 85TH ST 90045
Certificate Information: 6457 W 85TH ST 90045
- Application / Permit
- 21016-20000-20108
- Plan Check / Job No.
- B21VN10263
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) LAUNDRY ROOM TO BATHROOM AND CONVERT (E) BATHROOM TO LAUNDRY & POWDER ROOM. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- Permit Finaled on 4/14/2023
Permit Application Status History
| Submitted | 8/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 8/14/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 9/29/2021 | APPLICANT |
| Plan Check Approved | 4/11/2022 | GURUNATH NESARAJAH |
| Issued | 4/26/2022 | APPLICANT |
| Permit Finaled | 4/14/2023 | HERBERT GIRON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Green Design Builders Inc; Lic. No.: 1058542-B | 292 S LA CIENAGA BLVD #102 BEVERLY HILLS, CA 90211 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 5/18/2022 | Partial Inspection | BOBBY KEY |
| Gas Test | 1/26/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/10/2023 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 2/10/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 2/10/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 2/10/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 2/17/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/17/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 2/17/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 2/27/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/27/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 4/5/2023 | Corrections Issued | HERBERT GIRON |
| Final | 4/5/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 4/5/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 4/5/2023 | Approved | HERBERT GIRON |
| Final | 4/14/2023 | Permit Finaled | HERBERT GIRON |