6455 W 85TH ST 90045
Certificate Information: 6455 W 85TH ST 90045
- Application / Permit
- 21016-20000-20106
- Plan Check / Job No.
- B21VN10263
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19' 8" X 19' 8" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 8/14/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 9/29/2021 | APPLICANT |
| Plan Check Approved | 4/11/2022 | GURUNATH NESARAJAH |
| Issued | 4/26/2022 | APPLICANT |
| CofO in Progress | 4/14/2023 | HERBERT GIRON |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
| CofO Issued | 4/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/4/2021 | PABLO ESTRADA |
| ZI | Cleared | 10/4/2021 | PABLO ESTRADA |
| Address approval | Cleared | 10/6/2021 | DINAH GARIN |
| Sewer availability | Cleared | 10/6/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 3/28/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Green Design Builders Inc; Lic. No.: 1058542-B | 292 S LA CIENAGA BLVD #102 BEVERLY HILLS, CA 90211 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/27/2022 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 6/6/2022 | Conditional Approval | RICHARD STEINBACH |
| Sewer | 6/6/2022 | Approved | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 6/10/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 6/24/2022 | Partial Inspection | RICHARD STEINBACH |
| Underground Mechanical | 7/7/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/20/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 7/26/2022 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 9/26/2022 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 9/26/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Conditional Approval | HERBERT GIRON |
| Green Building Rough | 10/17/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/24/2022 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 10/24/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 10/24/2022 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/2/2022 | Approved | HERBERT GIRON |
| Insulation | 11/2/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 11/7/2022 | Conditional Approval | HERBERT GIRON |
| Shower Pan | 11/7/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 11/14/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 11/14/2022 | Approved | HERBERT GIRON |
| Gas Test | 1/26/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 4/5/2023 | Corrections Issued | HERBERT GIRON |
| Final | 4/5/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 4/5/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 4/5/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 4/5/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 4/5/2023 | Approved | HERBERT GIRON |
| Special/Order Compliance | 4/5/2023 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 4/14/2023 | Approved | HERBERT GIRON |
| Final | 4/14/2023 | OK to Issue CofO | HERBERT GIRON |
| HVAC-Final | 4/14/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 4/14/2023 | Approved | HERBERT GIRON |