21801 W ROSCOE BLVD 91304
Certificate Information: 21801 W ROSCOE BLVD 91304
- Application / Permit
- 21016-20000-20015
- Plan Check / Job No.
- B21VN10227
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- REPAIR AND REPLACE DRY ROT DAMAGED FLOOR FRAMING AT BALCONIES AND WALKWAY. REPAIR AND REPLACE DRY ROT DAMAGED ROOF FRAMNG ABOVE GARAGE. ALL WORK PER ENGINEER. SEE COMMENTS. COMPLY WITH DEPARTMENT ORDER effective date 05/25/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- Issued on 11/1/2021
Permit Application Status History
| Submitted | 8/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 8/11/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 9/13/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/29/2021 | JEROME MAGAT PALMA |
| Issued | 11/1/2021 | APPLICANT |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/17/2021 | STEVEN WECHSLER |
Contact Information
| Contractor | Uptown Renovations Inc; Lic. No.: 1001937-B | 5912 WHEELHOUSE LN AGOURA HILLS, CA 91301 |
| Engineer | Kardjian,, Vahe Matios; Lic. No.: C40821 | 1112 W BURBANK BLVD STE 301 BURBANK, CA 91506 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/8/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 1/27/2022 | Approved | JEFFREY FULTON |
| Wood Frame | 1/27/2022 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 3/9/2022 | Partial Inspection | JEFFREY FULTON |
| Interior/Exterior Lathing | 3/23/2022 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 3/23/2022 | Approved | JEFFREY FULTON |
| Interior/Exterior Lathing | 3/31/2022 | Approved | JEFFREY FULTON |
| Wood Frame | 6/22/2022 | Partial Inspection | JEFFREY FULTON |
| Interior/Exterior Lathing | 6/29/2022 | Approved | JEFFREY FULTON |
| Final | 11/2/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 11/2/2022 | Not Ready for Inspection | JEFFREY FULTON |