4368 S PURDUE AVE 90066

Certificate Information: 4368 S PURDUE AVE 90066

Application / Permit
21016-20000-19998
Plan Check / Job No.
B21VN10200
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 20' x 19' DETACHED GARAGE INTOA (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP
Permit Issued
Issued on 10/27/2021
Issuing Office
Current Status
CofO Issued on 5/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2021 APPLICANT
Assigned to Plan Check Engineer 8/11/2021 JEFFREY TANGONAN
Corrections Issued 8/11/2021 JEFFREY TANGONAN
Building Plans Picked Up 8/16/2021 APPLICANT
Applicant returned to address corrections 9/30/2021 JEFFREY TANGONAN
Issued 10/27/2021 APPLICANT
CofO in Progress 5/4/2022 PATRICK QUALEY
Permit Finaled 5/10/2022 DANIEL ORRANTE
Permit Finaled 5/10/2022 DANIEL ORRANTE
CofO Issued 5/10/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/17/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/17/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 8/17/2021 HISASHI KOBAYAKAWA
Construction near power lines Cleared 10/26/2021 RIDWAN HARDY

Contact Information

Contractor Sb Construction & Remodeling Inc; Lic. No.: 1061509-B P O BOX 260915      ENCINO, CA 91426

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/15/2021 Approved ENRIQUE MIRELES
Pre-Inspection 11/15/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/19/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/19/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 11/30/2021 Partial Approval JOHN KAYON
Interior/Exterior Lathing 11/30/2021 Approved JOHN KAYON
PLUMBING-Rough 11/30/2021 Partial Approval JOHN KAYON
BUILDING-Rough-Frame 12/2/2021 Approved JOHN KAYON
Green Building Rough 12/2/2021 Approved JOHN KAYON
HVAC-Rough 12/2/2021 Approved JOHN KAYON
Insulation 12/2/2021 Approved JOHN KAYON
PLUMBING-Rough 12/2/2021 Approved JOHN KAYON
Drywall Nailing 12/7/2021 Approved JOHN KAYON
Interior/Exterior Lathing 12/7/2021 Approved JOHN KAYON
Final 1/3/2022 Corrections Issued EVAN COOPER
Green Building Final 1/3/2022 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/3/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 1/3/2022 Approved EVAN COOPER
Final 1/25/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 1/25/2022 Approved ENRIQUE MIRELES
Final 4/21/2022 Corrections Issued DAVID FEILER
Final 4/27/2022 Corrections Issued PATRICK QUALEY
Final 5/4/2022 OK to Issue CofO PATRICK QUALEY