11611 W HATTERAS ST 91601

Certificate Information: 11611 W HATTERAS ST 91601

Application / Permit
21016-20000-19886
Plan Check / Job No.
B21VN10161
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 34'2" X 18' GARAGE/WORKSHOP TO ACCESSORY DWELLING UNIT AND ADD 14'1" x 5'10" ADDITION PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/6/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2021 APPLICANT
Assigned to Plan Check Engineer 8/6/2021 JEFFREY TANGONAN
Corrections Issued 8/7/2021 JEFFREY TANGONAN
Building Plans Picked Up 8/11/2021 APPLICANT
Plan Check Approved 10/1/2021 JEFFREY TANGONAN
Issued 9/6/2022 APPLICANT
CofO in Progress 8/17/2023 RYAN SALAZAR
CofO Issued 9/19/2023 RUBEN SALAS
Permit Finaled 9/19/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/12/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/12/2021 CARLOS AGUILERA
Permit Cleared 8/12/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/12/2021 CARLOS AGUILERA
Sewer availability Cleared 8/12/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/29/2022 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 10/3/2022 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 10/4/2022 Approved THOMAS FINNILA
Footing/Foundation/Slab 10/5/2022 Not Ready for Inspection THOMAS FINNILA
Sewer 10/11/2022 Approved CALEB MEISTER
Underground Mechanical 10/11/2022 Partial Approval CALEB MEISTER
BUILDING-Rough-Frame 10/25/2022 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/25/2022 Approved JACK KARGODORIAN
Green Building Rough 10/25/2022 Approved JACK KARGODORIAN
ELECTRICAL-Rough 11/10/2022 Approved JACK KARGODORIAN
HVAC-Rough 11/10/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 11/10/2022 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 11/10/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 11/14/2022 Approved JACK KARGODORIAN
Drywall Nailing 11/29/2022 Approved JACK KARGODORIAN
Insulation 11/29/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/6/2022 Partial Approval JACK KARGODORIAN
ELECTRICAL-Final 8/16/2023 Approved RYAN SALAZAR
Final 8/16/2023 OK to Issue CofO RYAN SALAZAR
Footing/Foundation/Slab 8/16/2023 Approved RYAN SALAZAR
Green Building Final 8/16/2023 Approved RYAN SALAZAR
HVAC-Final 8/16/2023 Approved RYAN SALAZAR
PLUMBING-Final 8/16/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 8/16/2023 Approved RYAN SALAZAR