2833 S BEDFORD ST 90034

Certificate Information: 2833 S BEDFORD ST 90034

Application / Permit
21016-20000-19730
Plan Check / Job No.
B21VN10023
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 16'-0" X 18'-0" DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 8/22/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 ARTIN ZARUKIAN
Corrections Issued 9/7/2021 ARTIN ZARUKIAN
Quality Review Completed 9/14/2021 STEVEN KIM
Applicant returned to address corrections 1/11/2022 ARTIN ZARUKIAN
Applicant returned to address corrections 3/26/2022 ARTIN ZARUKIAN
Applicant returned to address corrections 5/19/2022 ARTIN ZARUKIAN
Building Plans Picked Up 5/24/2022 APPLICANT
Applicant returned to address corrections 6/23/2022 ARTIN ZARUKIAN
Applicant returned to address corrections 7/27/2022 ARTIN ZARUKIAN
Plan Check Approved 8/22/2022 ARTIN ZARUKIAN
Issued 8/22/2022 APPLICANT
CofO in Progress 6/16/2023 JEREMY TODD
Permit Finaled 6/27/2023 DANIEL ORRANTE
CofO Issued 6/27/2023 DANIEL ORRANTE
Permit Finaled 6/27/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/30/2021 JEANIE LAM
Sewer availability Cleared 11/30/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/2/2022 JEANIE LAM
Construction near power lines Cleared 2/18/2022 RIDWAN HARDY

Contact Information

Contractor Future Builders & Design Inc; Lic. No.: 1058468-B 20252 ARCHWOOD ST      WINNETKA, CA 91306
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/20/2022 Partial Approval EVAN COOPER
Sewer 9/20/2022 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 9/27/2022 Approved EVAN COOPER
ELECTRICAL-Rough 11/15/2022 Approved CLAYTON GRAHAM
HVAC-Rough 11/15/2022 Not Ready for Inspection CLAYTON GRAHAM
PLUMBING-Rough 11/15/2022 Approved CLAYTON GRAHAM
Underground Mechanical 11/15/2022 Corrections Issued CLAYTON GRAHAM
BUILDING-Rough-Frame 11/22/2022 Not Ready for Inspection MICHAEL PELHAM
ELECTRICAL-Rough 11/22/2022 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Approved MICHAEL PELHAM
Green Building Rough 11/22/2022 Not Ready for Inspection MICHAEL PELHAM
HVAC-Rough 11/22/2022 Corrections Issued MICHAEL PELHAM
MERV13>=Rough 11/22/2022 Approved MICHAEL PELHAM
Sewer 11/22/2022 Approved MICHAEL PELHAM
Special/Order Compliance 11/22/2022 Partial Inspection JEREMY TODD
Interior/Exterior Lathing 12/8/2022 Approved JEREMY TODD
Shower Pan 12/8/2022 Approved JEREMY TODD
Interior/Exterior Lathing 12/14/2022 Approved JEREMY TODD
BUILDING-Rough-Frame 12/20/2022 Approved CLAYTON GRAHAM
Green Building Rough 12/20/2022 Approved CLAYTON GRAHAM
HVAC-Rough 12/20/2022 Approved CLAYTON GRAHAM
Insulation 12/20/2022 Approved CLAYTON GRAHAM
Drywall Nailing 12/27/2022 Approved JEREMY TODD
Final 5/23/2023 Corrections Issued JEREMY TODD
Green Building Final 5/23/2023 Not Ready for Inspection JEREMY TODD
MERV13>=Final 5/23/2023 Approved JEREMY TODD
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Not Ready JEREMY TODD
Smoke Detectors 5/23/2023 Approved JEREMY TODD
Final 6/6/2023 Corrections Issued JEREMY TODD
Green Building Final 6/6/2023 Approved JEREMY TODD
SGSOV-Seismic Gas S/O Valve 6/6/2023 SGSOV Approved JEREMY TODD
ELECTRICAL-Final 6/9/2023 Approved JEREMY TODD
Final 6/9/2023 Corrections Issued JEREMY TODD
HVAC-Final 6/9/2023 Approved JEREMY TODD
PLUMBING-Final 6/9/2023 Approved JEREMY TODD
Final 6/15/2023 OK to Issue CofO JEREMY TODD