14603 W HATTERAS ST 91411
Certificate Information: 14603 W HATTERAS ST 91411
- Application / Permit
- 21016-20000-19703
- Plan Check / Job No.
- B21VN10003
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND STORAGE ROOM TO ACCESSORY DWELLING UNIT (680 SQ FT) PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Current Status
- CofO Issued on 3/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 8/7/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/11/2021 | APPLICANT |
| Plan Check Approved | 8/30/2021 | JEROME MAGAT PALMA |
| Issued | 8/31/2021 | APPLICANT |
| CofO in Progress | 8/23/2022 | CALEB MEISTER |
| Permit Finaled | 3/30/2023 | DANIEL ORRANTE |
| CofO Issued | 3/30/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/30/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/12/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/1/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 2/1/2022 | Approved | ALAN MORELOS |
| Footing/Foundation/Slab | 2/3/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 2/3/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 2/17/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 2/17/2022 | Approved | ALAN MORELOS |
| Special/Order Compliance | 2/17/2022 | Corrections Issued | ALAN MORELOS |
| BUILDING-Rough-Frame | 2/18/2022 | Partial Approval | RICHARD DOCKUS |
| Green Building Rough | 2/18/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 2/18/2022 | Approved | RICHARD DOCKUS |
| Insulation | 2/23/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 2/24/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 3/1/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 3/1/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 3/9/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 5/17/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 5/17/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 5/17/2022 | Corrections Issued | RICHARD DOCKUS |
| Smoke Detectors | 5/17/2022 | Approved | RICHARD DOCKUS |
| Final | 5/18/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 5/18/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Approved | RICHARD DOCKUS |
| Final | 8/9/2022 | No Access for Inspection | RICHARD DOCKUS |
| Final | 8/18/2022 | Conditional Approval | CALEB MEISTER |
| Final | 8/23/2022 | OK to Issue CofO | CALEB MEISTER |