1946 N TAFT AVE 90068
Certificate Information: 1946 N TAFT AVE 90068
- Application / Permit
- 21016-20000-19630
- Plan Check / Job No.
- X21VN04950
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing (23) Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone (VHFHSZ). For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roofing Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0(b)2B.
- Permit Issued
- Issued on 7/29/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/12/2021
Permit Application Status History
| No Progress | 7/28/2021 | BLANCA MORALES |
| Issued | 7/29/2021 | APPLICANT |
| Permit Finaled | 9/11/2021 | EUGENE CASSIDY |
Permit Application Clearance Information
| HPOZ | Cleared | 7/29/2021 | DEEPEAKA DHALIWAL |
Contact Information
| Contractor | Approved Contractor Inc; Lic. No.: 952272-B | 9015 ETON AVENUE UNIT D CANOGA PARK, CA 91304 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Conditional Approval | RAUL BARAJAS |
| Final | 8/9/2021 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 8/9/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 8/12/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 8/12/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 8/24/2021 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 8/24/2021 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 8/24/2021 | Approved | RAUL BARAJAS |
| Final | 9/11/2021 | Permit Finaled | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/11/2021 | SGSOV Approved | EUGENE CASSIDY |