6715 N COSTELLO AVE 91405

Certificate Information: 6715 N COSTELLO AVE 91405

Application / Permit
21016-20000-19572
Plan Check / Job No.
B21VN09893
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convert Existing 1-story Garage and Recreation Room to an Accessory Dwelling Unit
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/30/2021 CARLOS MONTES
Corrections Issued 7/31/2021 PRANITA SHAH
Applicant returned to address corrections 9/14/2021 CARLOS MONTES
Applicant returned to address corrections 10/5/2021 CARLOS MONTES
Plan Check Approved 1/6/2022 CARLOS MONTES
Issued 1/12/2022 APPLICANT
CofO in Progress 1/11/2023 RYAN SALAZAR
Permit Finaled 2/14/2023 MICHAEL SMITH
CofO Issued 2/14/2023 MICHAEL SMITH
Permit Finaled 2/14/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/13/2021 CARLOS AGUILERA
Sewer availability Cleared 9/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/15/2021 CARLOS AGUILERA
Construction within easement Cleared 12/30/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/20/2022 Approved RICHARD DOCKUS
Pre-Inspection 1/27/2022 Approved RICHARD DOCKUS
Footing/Foundation/Slab 2/7/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 2/11/2022 Off-Hour Fees Due
PLUMBING-Rough 2/11/2022 Corrections Issued ALAN MORELOS
PLUMBING-Rough 2/11/2022 Off-Hour Fees Due
ELECTRICAL-Rough 2/24/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 2/24/2022 Not Ready for Inspection RICHARD DOCKUS
Sewer 2/24/2022 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 4/8/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 4/8/2022 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 7/27/2022 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Partial Approval JENNIFER RABUCHIN
Insulation 7/27/2022 Partial Approval JENNIFER RABUCHIN
Smoke Detectors 7/27/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/21/2022 Approved KATHRYN BUTTERWORTH
HVAC-Rough 10/31/2022 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 11/23/2022 Approved RYAN SALAZAR
PLUMBING-Rough 12/5/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/12/2022 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Final 12/12/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/19/2022 Approved RYAN SALAZAR
Final 12/30/2022 Corrections Issued RYAN SALAZAR
Green Building Final 12/30/2022 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/30/2022 SGSOV Approved RYAN SALAZAR
ELECTRICAL-Final 1/11/2023 Approved RYAN SALAZAR
Final 1/11/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 1/11/2023 Approved RYAN SALAZAR
HVAC-Final 1/11/2023 Approved RYAN SALAZAR