6715 N COSTELLO AVE 91405
Certificate Information: 6715 N COSTELLO AVE 91405
- Application / Permit
- 21016-20000-19572
- Plan Check / Job No.
- B21VN09893
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert Existing 1-story Garage and Recreation Room to an Accessory Dwelling Unit
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2021 | CARLOS MONTES |
| Corrections Issued | 7/31/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 9/14/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 10/5/2021 | CARLOS MONTES |
| Plan Check Approved | 1/6/2022 | CARLOS MONTES |
| Issued | 1/12/2022 | APPLICANT |
| CofO in Progress | 1/11/2023 | RYAN SALAZAR |
| Permit Finaled | 2/14/2023 | MICHAEL SMITH |
| CofO Issued | 2/14/2023 | MICHAEL SMITH |
| Permit Finaled | 2/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/13/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | CARLOS AGUILERA |
| Construction within easement | Cleared | 12/30/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/20/2022 | Approved | RICHARD DOCKUS |
| Pre-Inspection | 1/27/2022 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 2/7/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 2/11/2022 | Off-Hour Fees Due | |
| PLUMBING-Rough | 2/11/2022 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Rough | 2/11/2022 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 2/24/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 2/24/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Sewer | 2/24/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 4/8/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 4/8/2022 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 7/27/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 7/27/2022 | Partial Approval | JENNIFER RABUCHIN |
| Smoke Detectors | 7/27/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/21/2022 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 10/31/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 11/23/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 12/5/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/12/2022 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Final | 12/12/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/19/2022 | Approved | RYAN SALAZAR |
| Final | 12/30/2022 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 12/30/2022 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 1/11/2023 | Approved | RYAN SALAZAR |
| Final | 1/11/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 1/11/2023 | Approved | RYAN SALAZAR |
| HVAC-Final | 1/11/2023 | Approved | RYAN SALAZAR |