23662-23664 W COMMUNITY ST 91304
Certificate Information: 23662-23664 W COMMUNITY ST 91304
- Application / Permit
- 21016-20000-19481
- Plan Check / Job No.
- B21VN09835
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ECPC: CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/13/2021
- Issuing Office
- Current Status
- CofO Issued on 11/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2021 | JESSE ARELLANO |
| Corrections Issued | 8/3/2021 | JESSE ARELLANO |
| Plan Check Approved | 8/31/2021 | JESSE ARELLANO |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| Issued | 11/13/2021 | APPLICANT |
| CofO in Progress | 10/31/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 11/2/2022 | JOHN JANSON |
| CofO Issued | 11/2/2022 | JOHN JANSON |
| Permit Finaled | 11/2/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/10/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | CARLOS AGUILERA |
| Specific Plan | Cleared | 8/24/2021 | WILLIAM CABRERA |
| Green Code | Cleared | 8/31/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/9/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 6/10/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/23/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/23/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 6/23/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/23/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Sewer | 6/23/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/28/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 6/28/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/28/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/28/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 7/1/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/1/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 7/13/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 7/13/2022 | Partial Inspection | JESUS PINEDA |
| Wood Frame | 7/13/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 7/18/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 7/18/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/26/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 9/26/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 9/26/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 9/26/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/26/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 10/25/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 10/28/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |