11331 W CAMARILLO ST 91602

Certificate Information: 11331 W CAMARILLO ST 91602

Application / Permit
21016-20000-19330
Plan Check / Job No.
B21VN09760
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
INTERIOR AND EXTERIOR ALTERATION TO (E) RETAIL BUILDING WHICH INCLUDES ALTERATION TO THE (E) ACCESSIBLE RESTROOMS' FINISHED FLOOR, WALLS, AND CEILING, AND ALTERATION TO THE EXTERIOR WALL OF THE (E) BUILDING . WORK PER ENGINEER.
Permit Issued
Issued on 8/11/2022
Issuing Office
Metro
Current Status
Issued on 8/11/2022

Permit Application Status History

Submitted 8/1/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 COLIN LOREDO
Corrections Issued 9/8/2021 COLIN LOREDO
Quality Review Completed 9/17/2021 OMID HEDAYAT
Building Plans Picked Up 9/28/2021 APPLICANT
Disabled Access Plans Picked Up 9/28/2021 APPLICANT
Green Plans Picked Up 9/28/2021 APPLICANT
Plan Check Approved 3/14/2022 COLIN LOREDO
Issued 8/11/2022 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 9/30/2021 TERRI OSBORNE
ZA Case Cleared 9/30/2021 TERRI OSBORNE
ZA Case Cleared 9/30/2021 TERRI OSBORNE
DAS Clearance Cleared 2/18/2022 NORLITO MEDRANO
Green Code Cleared 2/23/2022 MICHAEL AYERS

Contact Information

Contractor Padelford A J & Son Inc; Lic. No.: 222840-B P O BOX 185      ARTESIA, CA 907020185
Engineer Provenghi,, Steven Guido; Lic. No.: S3888 8522 ACACIA DR      CYPRESS, CA 90630

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/23/2022 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 9/28/2022 Approved ROBERT DAVIS
Footing/Foundation/Slab 9/28/2022 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 10/12/2022 Conditional Approval ROBERT DAVIS
Green Building Rough 11/15/2022 Not Ready for Inspection ROBERT DAVIS
Wood Frame 11/15/2022 Corrections Issued ROBERT DAVIS
Deputy Drilled-In Anchors 2/23/2023 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 2/28/2023 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 3/2/2023 Conditional Approval ROBERT DAVIS
Green Building Rough 6/28/2023 Not Ready for Inspection ROBERT DAVIS
Wood Frame 6/28/2023 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 7/19/2023 Conditional Approval ROBERT DAVIS
Drywall Nailing 10/9/2025 Partial Inspection ROBERT DAVIS
Final 10/9/2025 Not Ready for Inspection ROBERT DAVIS
Green Building Final 10/9/2025 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 10/9/2025 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 10/9/2025 Partial Approval ROBERT DAVIS
Reinforced Masonry Frame 10/9/2025 Partial Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 10/9/2025 Not Ready for Inspection ROBERT DAVIS
Structural Steel Frame 10/9/2025 Partial Inspection ROBERT DAVIS
Wood Frame 10/9/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 10/21/2025 Partial Approval ROBERT DAVIS
Green Building Rough 10/21/2025 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 10/29/2025 Not Ready for Inspection ANDREW DORSO
Wood Frame 10/29/2025 Partial Inspection ANDREW DORSO
Green Building Rough 12/2/2025 Not Ready for Inspection JEFFREY DURAN
Wood Frame 12/2/2025 Corrections Issued JEFFREY DURAN